Which one of the following best describes a project issue?
Which one of the following best describes a project issue?
A . A major problem that requires formal escalation.
B . A problem that the project manager has to deal with on a day-to-day basis.
C . An uncertain event that may or may not occur.
D . An opportunity that occurs through change control.
Answer: A
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	