Which of the following would achieve the HIGHEST level of testing independence for a project’s system test level?
Which of the following would achieve the HIGHEST level of testing independence for a project’s system test level?
A . Training developers to design good tests for the test team to execute.
B . Outsourcing test design and execution to a different company.
C . Having the company’s independent test team design and execute the tests.
D . Minimising contact between testers and developers during test design to avoid bias.
Answer: A