Which of the following should be updated before requesting approval again?

A change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed.

Which of the following should be updated before requesting approval again?
A . Scope of change
B . Risk level
C . Rollback plan
D . End user acceptance

Answer: C