Which of the following should be updated before requesting approval again?

A change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed.

Which of the following should be updated before requesting approval again?
A . Scope of change
B. Risk level
C. Rollback plan
D. End user acceptance

Answer: C

Explanation:

The rollback plan should be updated before requesting approval again. A rollback plan is a plan for undoing a change if it causes problems, and it is an important part of any change management process. If the change advisory board did not approve the requested change due to the lack of alternative actions if implementation failed, then updating the rollback plan would be the best way to address this concern.

Latest 220-1102 Dumps Valid Version with 81 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments