Which of the following must be in place before implementing a BCP?
Which of the following must be in place before implementing a BCP?
A . SLA
B. AUP
C. NDA
D. BIA
Answer: D
Explanation:
A Business Impact Analysis (BIA) is a critical component of a Business Continuity Plan (BCP). It identifies and prioritizes critical business functions and determines the impact of their disruption.
Reference: CompTIA Security+ Study Guide 601, Chapter 10
Latest SY0-601 Dumps Valid Version with 396 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments