Which of the following is the correct sequence for the stages of a linear project life cycle?
Which of the following is the correct sequence for the stages of a linear project life cycle?
A . Deployment, Concept, Definition, Transition.
B . Concept, Transition, Definition, Deployment.
C . Concept, Definition, Deployment, Transition.
D . Transition, Definition, Deployment, Concept
Answer: C