Which of the following is an important part of the change request process for which the administrator still must plan?

A network administrator wants to plan a major OS upgrade of the router, which acts as a default gateway in an organization. The administrator has documented the purpose of the change, scoped the change, and completed a comprehensive risk analysis.

Which of the following is an important part of the change request process for which the administrator still must plan?
A . Inform management regarding the anticipated amount of downtime
B . Document a backout plan to roll back changes to the router
C . Configure a redundant data path to eliminate downtime
D . Make the downtime window larger than actually anticipated

Answer: B