Which of the following is a part of change control?
Which of the following is a part of change control?
A . Requests for change are realised.
B . Requests for change are mitigated.
C . Requests for change are evaluated.
D . Requests for change are resolved.
Answer: C
Latest APM-PFQ Dumps Valid Version with 354 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
                             Subscribe
                            
                        
                                            
                             Login                        
                    
                        0 Comments                    
                                        
                     Inline Feedbacks                    
                    View all comments
                 
	