Which of the following has the typical formal review activities in the correct sequence?

Which of the following has the typical formal review activities in the correct sequence?
A . Kick-off, review meeting, planning, follow-up.
B . Kick-off, planning, review meeting, re-work.
C . Planning, kick-off, individual preparation, review meeting.
D . Planning, individual preparation, follow-up, re-work.

Answer: C

Explanation:

The correct sequence is: planning, kick-off, individual preparation, review meeting, re-work, follow-up. All of the other options have either the activities in the wrong order or activities missing from the strict flow.