Which of the following documents did the client provide to the project manager?

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan.

Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?
A . RFP
B . WBS
C . SLA
D . SOW

Answer: D

Explanation:

The client provided a statement of work (SOW) to the project manager and suggested that the project manager and team just need to execute the plan. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.