Which of the following documents contains the design team’s interpretation of the Owner’s Project Requirements?

Which of the following documents contains the design team’s interpretation of the Owner’s Project Requirements?
A . Basis of Design (BOD)
B . Simple Box Energy Model Analysis
C . System’s manual
D . Integrated Project Delivery report

Answer: A

Explanation:

The Basis of Design (BOD) is the document that contains the design team’s interpretation of the Owner’s Project Requirements (OPR). The BOD describes the proposed systems and how they will meet the OPR, as well as the assumptions and criteria used for the design. The BOD is a key document for the Integrative Process credit and the Enhanced Commissioning credit in LEED BD+C12.

Reference: LEED BD+C Reference Guide, Integrative Process, page 301; LEED BD+C Reference Guide, Enhanced Commissioning, page 681