Which of the following change management practices would MOST likely have prevented this outage?

Ann. a network engineer is performing an after-hours upgrade on a network switch During the activity. Ann notices an unrelated setting she believes is misconfigured She decides to change the setting during the upgrade which causes an outage.

Which of the following change management practices would MOST likely have prevented this outage?
A . Risk analysis
B . Change board approval
C . Scoping the change
D . End-user acceptance

Answer: C