As a result of an approved change, the project manager updates the project plan with the newest project end date.
Which of the following change control processes should the project manager complete NEXT?
A . Document the request in the change control log.
B . Communicate the change deployment.
C . Conduct an impact assessment.
D . Implement the change.
Answer: B
Explanation:
The project manager should communicate the change deployment next after updating the project plan with the newest project end date as a result of an approved change. Communicating the change deployment involves informing all relevant parties about when and how the change will be implemented and what are the expected outcomes and benefits. Communicating the change deployment can help to ensure alignment, readiness, and support for the change and avoid any confusion or resistance.
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund