Which a following technique is the project manager utilizing?

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely.

Which a following technique is the project manager utilizing?
A . Process moving
B . Brainstorming
C . Interview
D . Focus group

Answer: D

Explanation:

A focus group is a technique that involves bringing together a group of stakeholders and facilitating a discussion to elicit their opinions, needs, and expectations about the project. This technique can help to gather requirements from stakeholders in an interactive and collaborative way1, p. 67