Which a following technique is the project manager utilizing?
To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely.
Which a following technique is the project manager utilizing?
A . Process moving
B . Brainstorming
C . Interview
D . Focus group
Answer: D
Explanation:
A focus group is a technique that involves bringing together a group of stakeholders and facilitating a discussion to elicit their opinions, needs, and expectations about the project. This technique can help to gather requirements from stakeholders in an interactive and collaborative way1, p. 67
Latest PK0-005 Dumps Valid Version with 81 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments