Exam4Training

When should refining of the Product Backlog occur? (choose the best two answers)

When should refining of the Product Backlog occur? (choose the best two answers)
A . The Product Owner must do this as essential work in Sprint 0.
B. The Product Owner does this between the end of the previous Sprint and the start of the next.
C. The Product Owner and the Developers do it in the current Sprint if they have been unable to do it in preceding Sprints.
D. The Product Owner and the Developers can refine the Product Backlog during any Sprint as needed, ideally in advance of the upcoming Sprint.
E. The Business Analysts prepare items be worked on at least 1 Sprint ahead of development.

Answer: C,D

Explanation:

Product Backlog refinement is a continuous activity. When an item is at the top of the backlog, which means it will be developed in the near future, more refinements are usually needed to make sure it is clear and contains just enough details (not all possible details). It’s preferred to have the items that will be selected in the Sprint Backlog completely refined before Sprint Planning; however, it’s OK to have more refinement done during the development. Remember that there’s no such thing as Sprint 0 and there’s no time between two Sprints that can be spent on something such as refinement. The team is also cross-functional and does the a-z of the work needed for each item, including refinement; they don’t use people from other parts of the company

Latest PSPO-II Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version