Exam4Training

Whattasks are listed by default for contingent workers in the My Tasks side panel of the Manage My Timesheet app?

Whattasks are listed by default for contingent workers in the My Tasks side panel of the Manage My Timesheet app?
A . None. Tasks must be manually added using Maintain Data Entry Profiles.
B. Accounting objects, including WBS element and cost center
C. None. Tasks must be manually added using Manage My Tasks.
D. Non-project-related tasks, including administration, training, and travel time

Answer: B

Exit mobile version