What type of risk response has Adrian used in this example?
Adrian is the project manager of the NHP Project. In her project there are several work packages that deal with electrical wiring. Rather than to manage the risk internally she has decided to hire a vendor to complete all work packages that deal with the electrical wiring. By removing the risk internally to a licensed electrician Adrian feels more comfortable with project team being safe.
What type of risk response has Adrian used in this example?
A . Mitigation
B . Transference
C . Avoidance
D . Acceptance
Answer: B