What is the appropriate action for the project manager to take?

A project manager is assigned to a new Workfront request. The request specifies that the management team’s sign-off is needed before the project can begin.

What is the appropriate action for the project manager to take?
A . Convert the issue into a project using a project template.
B . Email the management team and request their approval.
C . Use a customized approval process to route the issue for approval.

Answer: C

Explanation:

In Workfront, approval processes are designed to handle scenarios where certain team members must give formal approval before work can proceed. In this case, the project manager should set up a customized approval process that routes the request through the necessary stakeholders (management team) for their sign-off. This ensures proper governance and tracking.

Latest AD0-E903 Dumps Valid Version with 70 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments