What can you check using budget availability control?
You want to use budget availability control for your projects and internal orders.
What can you check using budget availability control? Note: There are 2 correct answers to this question.
A . The availability of funds using overall plan value
B . The availability of funds according to tolerance limits
C . The availability of funds in object currency
D . The availability of funds on period level
Answer: B,C