The result of proper design and operation of buildings and neighborhoods is an increase in energy
The result of proper design and operation of buildings and neighborhoods is an increase in energyA . supplyB . demandC . efficiencyD . consumptionView AnswerAnswer: C Explanation: The result of proper design and operation of buildings and neighborhoods is an increase in energy efficiency. Energy efficiency is the ratio of...
A new project is being built adjacent to a park with a 1/8 mi. (0.20 km) trail leading to an urban business district, which includes several retail shops and restaurants. This project qualifies for Location and Transportation Credits by
A new project is being built adjacent to a park with a 1/8 mi. (0.20 km) trail leading to an urban business district, which includes several retail shops and restaurants. This project qualifies for Location and Transportation Credits byA . maintaining open spaceB . reducing heat island effectC . providing...
During the materials specification, which of the following strategies can the owner take in order to achieve this goal?
An owner is looking to update the interior materials of the office while promoting a healthier indoor work environment using LEED strategies. During the materials specification, which of the following strategies can the owner take in order to achieve this goal?A . Specify salvaged materialsB . Specify low-cost materialsC ....
What do team members enhance by collaboration during the integrative process?
What do team members enhance by collaboration during the integrative process?A . Project durationB . Life-cycle costsC . Construction costsD . Efficiency and effectiveness of systemsView AnswerAnswer: D Explanation: The integrative process involves collaboration among all project team members, from initial planning through design and construction, to enhance the efficiency...
Which of the following principles is a part of the integrated process?
Which of the following principles is a part of the integrated process?A . Cradle-to-cradleB . Systems thinkingC . Project schedulingD . Building information modelingView AnswerAnswer: B Explanation: Systems thinking is a principle that is part of the integrated process, which is a collaborative and holistic approach to green building design,...
Which of the following facilitates the recharging of aquifers?
Which of the following facilitates the recharging of aquifers?A . Asphalt roadB . Pervious pavingC . Impervious pavingD . Concrete parking lotView AnswerAnswer: B Explanation: Pervious paving, also known as permeable paving, allows water to pass through it, facilitating the recharging of aquifers. This type of paving reduces runoff by...
What should the project team have done differently to avoid this error?
The LEED reviewer advised a project team that an inappropriate rating system was chosen for a newly constructed school in operation for one year and undergoing minor improvements. What should the project team have done differently to avoid this error?A . Allow the LEED Project Administrator sole responsibility to review...
Which of the following is a benefit of a building owner choosing to install a solar photovoltaic?
Which of the following is a benefit of a building owner choosing to install a solar photovoltaic?A . Lower liabilitiesB . Heat Island ReductionC . Decreased upfront building costD . Reduced greenhouse gas emissionsView AnswerAnswer: D Explanation: Installing a solar photovoltaic system can significantly reduce greenhouse gas emissions from a...
ASHRAE standards are applicable to which of the following LEED categories?
ASHRAE standards are applicable to which of the following LEED categories?A . Sustainable Sites and Energy and AtmosphereB . Materials and Resources and Sustainable SitesC . Water Efficiency and Indoor Environmental QualityD . Energy and Atmosphere and Indoor Environmental QualityView AnswerAnswer: D Explanation: ASHRAE stands for the American Society of...
Installing which of the following will increase the quantity of the rainwater that is discharged from a site?
Installing which of the following will increase the quantity of the rainwater that is discharged from a site?A . Vegetated roofB . Porous pavers for parking lotsC . Concrete sidewalks and parking areasD . Bioswales and ram gardens with native plantsView AnswerAnswer: C Explanation: Installing concrete sidewalks and parking areas...