Exam4Training

USGBC LEED AP BD+C LEED AP Building Design + Construction Online Training

Question #1

What is the maximum number of points a project pursuing LEED for New Construction can achieve under Location and Transportation Credit, Access to Quality Transit?

  • A . Two points
  • B . Three points
  • C . Four points
  • D . Five points

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

According to the LEED v4: Building Design + Construction Guide, the Location and Transportation Credit, Access to Quality Transit has two options: Option 1. Transit-Served Location and Option 2. Transit Service Quality. Option 1 can earn 1 to 4 points depending on the percentage of functional entries within walking distance of transit stops or stations. Option 2 can earn 1 point if the project meets the minimum weekday and weekend headways for bus, streetcar, or informal transit stops, or rail stations or ferry terminals. The maximum number of points a project can achieve under this credit is 4 points by meeting both options1.

References: LEED v4: Building Design + Construction Guide, Location and Transportation Credit, Access to Quality Transit, Requirements1

Question #2

Which of the following sinks is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction?

  • A . A sink in an office restroom
  • B . A sink in a school classroom
  • C . A sink in a hotel room bathroom
  • D . A sink in a shared office restroom

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

A sink in a hotel room bathroom is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction.According to the LEED v4 BD+C Reference Guide, a private lavatory faucet is defined as “a faucet that is not generally accessible and is used only by the building’s occupants and not by the public or visitors”1. A sink in an office restroom, a school classroom, or a shared office restroom are examples of public lavatory faucets, which have different baseline flow rates and requirements.

References: LEED v4 BD+C Reference Guide, Water Efficiency Category, WEc Indoor Water Use Reduction, page 681.

Question #3

Which one of the following represents quality transit service as defined in Location and Transportation Credit, Access to Quality Transit?

  • A . A bus stop served by two bus lines Monday through Friday, located 1/8 mi. (0.20 km) from the project building
  • B . A rail station served by one train line Monday through Sunday, located 1/2 mi. (0.80 km) fromthe project building
  • C . A rail station served by two train lines Monday through Sunday, located 1 mi. (1.60 km) from the project building
  • D . A private shuttle bus stop providing hourly service Monday through Friday to a rail station two hours away, located across the street from the project building

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

The Location and Transportation Credit, Access to Quality Transit requires projects to locate within walking distance of existing or planned transit stops that provide access to quality transit service1. Quality transit service is defined as transit service that meets the minimum weekday and weekend headways (time between vehicles) and hours of operation listed in Table 1 of the credit requirements2. According to Table 1, the minimum weekday headway for bus service is 15 minutes, and the minimum weekday headway for rail service is 10 minutes. The minimum weekend headway for both bus and rail service is 30 minutes. The minimum hours of operation for both bus and rail service are 6 a.m. to 8 p.m. on weekdays and 8 a.m. to 6 p.m. on weekends2. In addition, the credit requires projects to locate within a 1/4 mi. (0.40 km) walking distance of bus, streetcar, or rideshare stops or within a 1/2 mi. (0.80 km) walking distance of bus rapid transit stops, light or heavy rail stations, commuter rail stations, or ferry terminals1.

Option A does not represent quality transit service because it only has two bus lines that may not meet the minimum headway and hours of operation requirements. Option C does not represent quality transit service because it is beyond the maximum walking distance of 1/2 mi. (0.80 km) for rail stations. Option D does not represent quality transit service because it is a private shuttle bus that does not qualify as a public transportation service, and it provides hourly service that does not meet the minimum headway requirements. Option B represents quality transit service because it has a rail station that is within the maximum walking distance of 1/2 mi. (0.80 km) from the project building, and it has one train line that operates Monday through Sunday, which implies that it meets the minimum headway and hours of operation requirements.

References:

Access to Quality Transit

Access to Quality Transit – Canada Green Building Council

Question #4

The Required Breathing Zone Outdoor Airflow Vbz for a new banking facility is 0.120 CFM/ft2 (0.6 L/s/m2). If the team decides to attempt Increased Ventilation under Option 2 in the Indoor Environmental Quality Credit, Enhanced Indoor

Air Quality Strategies, what is the minimum Design Zone Outdoor Airflow?

  • A . 0.144 CFM/ft2 (0.73 (L/s)/m2)
  • B . 0.156 CFM/ft2 (0.79 (L/s)/m2)
  • C . 0.168 CFM/ft2 (0.85 (L/s)/m2)
  • D . 0.30 CFM/ft2 (1.5 (L/s)/m2)

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

This option requires the project to increase the breathing zone outdoor airflow by at least 20% above the minimum rates required by ASHRAE 62.1-2010. Therefore, the minimum design zone outdoor airflow is 0.120 CFM/ft2 x 1.2 = 0.144 CFM/ft2.

References: = [LEED v4: Building Design + Construction Guide], [Indoor Environmental Quality Credit: Enhanced Indoor Air Quality Strategies], [ASHRAE 62.1-2010 User’s Manual].

Question #5

Which of the following must be included in the Sustainable Sites Credit, Site Assessment?

  • A . A targeted Brownfield remedy plan
  • B . Historic preservation plan to include neighboring properties
  • C . Proximity of vulnerable populations to major sources of air pollution
  • D . The surrounding density within a 1/4 mi. (0.40 km) radius of the project boundary

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The correct answer is C. Proximity of vulnerable populations to major sources of air pollution.

According to the LEED v4.1 Reference Guide for Building Design and Construction, the Site Assessment credit requires projects to conduct and document a site inventory and analysis that covers the following topics1:

– Topography

– Hydrology

– Climate

– Vegetation

– Soils

– Human use

– Human health effects

The human health effects topic includes identifying the proximity of vulnerable populations, such as children, elderly, or low-income residents, to major sources of air pollution, such as highways, power plants, or industrial facilities. This information can help the project team design strategies to minimize the exposure of occupants and visitors to harmful pollutants and improve the indoor and outdoor air quality of the project1.

The other options are not required for the Site Assessment credit, although they may be relevant for other credits or prerequisites. A targeted Brownfield remedy plan is required for the Brownfields Remediation credit, which applies to projects located on sites contaminated by past uses1.A historic preservation plan to include neighboring properties is not required for any LEED credit, although projects that involve historic buildings or districts must comply with local regulations and standards for preservation1. The surrounding density within a 1/4 mi.(0.40 km) radius of the project boundary is not required for the Site Assessment credit, but it is used to calculate the points for the Surrounding Density and Diverse Uses credit, which encourages projects to locate in areas with high levels of existing development and mixed land uses1.

Question #6

What is the definition of the evapotranspiration rate?

  • A . Evaporation of onsite reuse water
  • B . Percentage of potable water usage for irrigation
  • C . Water loss from evaporation in micro irrigation systems
  • D . Amount of water loss in a vegetated surface in units of water depth

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

The evapotranspiration rate is the amount of water loss in a vegetated surface in units of water depth, such as millimeters or inches. It is a measure of the water demand of the plants and the climate conditions. It is used to calculate the baseline water use for irrigation in the Outdoor Water Use Reduction credit.

References:

• LEED v4 BD+C Reference Guide, page 5381

• Outdoor Water Use Reduction Credits in LEED v4 – HydroPoint2

Question #7

What type of project would benefit from showing compliance with Energy and Atmosphere Prerequisite, MinimumEnergy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

  • A . One in which the budget and timeline would benefit from simplified decision making and analysis during the project design
  • B . One in which the project team wants to explore the energy performance and load reduction effects of severalenvelope and lighting designs and mechanical systems
  • C . One in which the project team wants to achieve efficiency trade-offs between systems, offsetting the lower efficiency of one system by the improved efficiency of another
  • D . One in which the owner wants an estimate of the carbon reductions or lower operating costs (energy savings, demand charge savings) from energy strategies, beyond a simple calculation for individual energy conservation measures

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

This option allows the project to comply with the minimum energy performance prerequisite by following the prescriptive recommendations of the ASHRAE 50% Advanced Energy Design Guide (AEDG) for the applicable building type and climate zone1. This option simplifies the decision making and analysis process by providing clear and specific guidance on how to achieve 50% energy savings compared to the baseline standard2. This option alsoreduces the need for energy modeling and documentation, which can save time and money for the project3.

References: = [LEED v4: Building Design + Construction Guide], Minimum Energy Performance Calculator – ASHRAE 90.1 – 2010, 50 Percent AEDG Free Download – ASHRAE.

Question #8

A rectangular office building is located in an extremely humid climate and is shaded by very large adjacent buildings on all four sides.

If the building owner wants to decrease the annual energy cost for operating the building, which of the following would be the best design approach?

  • A . Install glazing with a higher solar heat gain factor
  • B . Install photovoltaic panels on the sides of the building
  • C . Increase outdoor air intake quantities during summer months
  • D . Recover waste energy through exhaust air energy recovery systems

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

The best design approach for the office building is D. Recover waste energy through exhaust air energy recovery systems.

This is because:

– Installing glazing with a higher solar heat gain factor would increase the cooling load and energy consumption of the building, especially in an extremely humid climate where heat gain is high1.

– Installing photovoltaic panels on the sides of the building would generate electricity from solar radiation, but it would not reduce the cooling load or energy consumption of the building, unless the electricity is used to power a heat pump or other cooling device2.

– Increasing outdoor air intake quantities during summer months would provide more fresh air to dilute the indoor pollutants and improve the indoor air quality, but it would not reduce the cooling load or energy consumption of the building, unless it is combined with a ventilation system that recovers waste energy from the exhaust air stream34.

An exhaust air energy recovery system (ERV) is a type of mechanical ventilation that uses a heat exchanger to transfer heat between two streams of air: one that enters the building and one that exits. The ERV pre-cools and dehumidifies the incoming ventilation air bysending the rejected heat into the exhaust airstream to cool the condenser coil at a lower temperature. This reduces both the cooling load and energy consumption of the building, as well as improving its indoor humidity levels34. An ERV can also provide some fresh outdoor air to meet ASHRAE Standard 62 ventilation rates5.

Therefore, an ERV is a more efficient and effective design approach than glazing, photovoltaic panels, or increased outdoor air intake quantities for reducing the annual energy cost for operating an office building in an extremely humid climate and shaded by very large adjacent buildings on all four sides.

References: 1: LEED v4: Building Design + Construction Guide – U.S. Green Building Council 2: LEED AP BD+C Exam | U.S. Green Building Council 3: Energy Recovery Systems – Nortek Air Solutions 4: Energy Recovery Ventilators – Greenheck 5: Mechanical Ventilation Types: Exhaust, Supply, Balanced & Energy Recovery

Question #9

For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include

  • A . verification that a weighted daily average has been used for each qualifying route
  • B . confirmation that functional entries of the project are within 3/4 mi. (1.20 km) of the stop
  • C . verification that a weighted building average has been used for each qualifying functional entry
  • D . confirmation that each qualifying route features paired route service (service in opposite directions)

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

This option requires the project team to calculate the weighted daily average of the number of trips per day for each qualifying route, using the formula provided in the LEED v4: Building Design + Construction Guide. This option ensures that the transit service frequency is accurately represented and meets the minimum thresholds for weekday and weekend trips, as shown in Table 1 and Table 2 of the guide.

References: = [LEED v4: Building Design + Construction Guide], Access to Quality Transit.

Question #10

Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?

  • A . 50,000 ft2 (4 645 m2) office project
  • B . 80,000 ft2 (7 432 m2) hospital project
  • C . 110,000 ft2 (10 219 m2) school project
  • D . 140,000 ft2 (13 006 m2) retail project

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide allows projects to follow the recommendations of the ASHRAE 50% Advanced Energy Design Guides (AEDGs) for different building types and climate zones. The AEDGs provide design guidance for buildings that use 50% less energy than those built to the requirements of the ANSI/ASHRAE/IES Standard 90.1-2004 commercial code1. However, not all building types and sizes are covered by the AEDGs. According to the LEED Reference Guide for Building Design and Construction2, the following building types and sizes are eligible for this option:

– Small to Medium Office buildings up to 100,000 ft2 (9 290 m2)

– Medium to Large Retail buildings up to 100,000 ft2 (9 290 m2)

– K-12 School buildings up to 200,000 ft2 (18 580 m2)

– Warehouse and Distribution Center buildings up to 500,000 ft2 (46 450 m2)

Therefore, among the given options, only the school project is eligible to pursue this option, as it falls within the size limit for the K-12 School AEDG3.

References:

LEED Reference Guide for Building Design and Construction v4

Minimum Energy Performance – ASHRAE 90.1 – 2010

ASHRAE 50% Advanced Energy Design Guide for K-12 School Buildings

Advanced Energy Design Guides | Department of Energy

Question #11

Which of the following could be considered diverted construction waste?

  • A . Excavated soil
  • B . Land-clearing debris
  • C . Alternative daily cover
  • D . Asphalt with aggregate

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4 Reference Guide for Building Design and Construction, diverted construction waste is defined as "materials that are diverted from disposal in landfills or incineration facilities and are instead reused, recycled, composted, or salvaged"1. Asphalt with aggregate is an example of a material that can be recycled and reused for paving or other applications. Excavated soil and land-clearing debris are excluded from the calculation of the total construction and demolition waste for the MR Credit Building Life-Cycle Impact Reduction1. Alternative daily cover is a material that is used to cover the surface of an active landfill at the end of each day to control odors, pests, and litter. It is not considered as diversion because it does not reduce the amount of waste sent to landfills2.

References: MR Credit Building Life-Cycle Impact Reduction, LEED v4 Reference Guide for Building Design and Construction3142

Question #12

A contractor is building a retirement community project. 30% of the building’s product costs were derived from reused/salvaged materials or met recycled content criteria.

Which of the following credits can the LEED AP submit towards certification?

  • A . Materials and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials
  • B . Materials and Resources Prerequisite, Construction and Demolition – Waste Management Planning
  • C . Materials and Resources Credit, Building Product Disclosure and Optimization – Material Ingredients
  • D . Materials and Resources Credit, Building Product Disclosure and Optimization – Environmental Product Declarations

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

The Materials and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials rewards projects that use materials that have optimized extraction processes by limiting or eliminating the extraction of new resources, the reuse of materials or the use of recycled materials1. According to the LEED Reference Guide for Building Design and Construction2, the credit has two options: Option 1. Raw Material Source and Extraction Reporting and Option 2. Leadership Extraction Practices. Option 1 requires the project to use at least 20 permanently installed products from at least five different manufacturers that have publicly released a report from their raw material suppliers which include extraction locations, a commitment to long-term ecologically responsible land use, a commitment to reducing environmental harms from extraction and/or manufacturing processes, and a commitment to meeting applicable standards or programs voluntarily that address responsible sourcing criteria2. Option 2 requires the project to use products that meet at least one of the responsible sourcing criteria below for at least 25%, by cost, of the total value of permanently installed building products in the project:

– Extended producer responsibility. Products purchased from a manufacturer (producer) that participates in an extended producer responsibility program or is directly responsible for extended producer responsibility.

– Bio-based materials. Bio-based products must meet the Sustainable Agriculture Network’s Sustainable Agriculture Standard. Bio-based raw materials must be tested using ASTM Test Method D6866 and be legally harvested, as defined by the exporting and receiving country. Exclude hide products, such as leather and other animal skin material.

– Wood products. Wood products must be certified by the Forest Stewardship Council or USGBC-approved equivalent.

– Materials reuse. Reused products must include salvaged, refurbished, or reused products.

– Recycled content. Recycled content is the sum of postconsumer recycled content plus one-half the preconsumer recycled content, based on cost. Products meeting recycled content criteria are valued at 100% of their cost for the purposes of credit achievement calculation.

– USGBC approved program. Other USGBC approved programs meeting leadership extraction criteria.

Therefore, among the given options, only Option A is relevant to the use of reused/salvaged materials or recycled content, as they can contribute to the materials reuse or recycled content criteria under Option

Question #12

A contractor is building a retirement community project. 30% of the building’s product costs were derived from reused/salvaged materials or met recycled content criteria.

Which of the following credits can the LEED AP submit towards certification?

  • A . Materials and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials
  • B . Materials and Resources Prerequisite, Construction and Demolition – Waste Management Planning
  • C . Materials and Resources Credit, Building Product Disclosure and Optimization – Material Ingredients
  • D . Materials and Resources Credit, Building Product Disclosure and Optimization – Environmental Product Declarations

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

The Materials and Resources Credit, Building Product Disclosure and Optimization – Sourcing of Raw Materials rewards projects that use materials that have optimized extraction processes by limiting or eliminating the extraction of new resources, the reuse of materials or the use of recycled materials1. According to the LEED Reference Guide for Building Design and Construction2, the credit has two options: Option 1. Raw Material Source and Extraction Reporting and Option 2. Leadership Extraction Practices. Option 1 requires the project to use at least 20 permanently installed products from at least five different manufacturers that have publicly released a report from their raw material suppliers which include extraction locations, a commitment to long-term ecologically responsible land use, a commitment to reducing environmental harms from extraction and/or manufacturing processes, and a commitment to meeting applicable standards or programs voluntarily that address responsible sourcing criteria2. Option 2 requires the project to use products that meet at least one of the responsible sourcing criteria below for at least 25%, by cost, of the total value of permanently installed building products in the project:

– Extended producer responsibility. Products purchased from a manufacturer (producer) that participates in an extended producer responsibility program or is directly responsible for extended producer responsibility.

– Bio-based materials. Bio-based products must meet the Sustainable Agriculture Network’s Sustainable Agriculture Standard. Bio-based raw materials must be tested using ASTM Test Method D6866 and be legally harvested, as defined by the exporting and receiving country. Exclude hide products, such as leather and other animal skin material.

– Wood products. Wood products must be certified by the Forest Stewardship Council or USGBC-approved equivalent.

– Materials reuse. Reused products must include salvaged, refurbished, or reused products.

– Recycled content. Recycled content is the sum of postconsumer recycled content plus one-half the preconsumer recycled content, based on cost. Products meeting recycled content criteria are valued at 100% of their cost for the purposes of credit achievement calculation.

– USGBC approved program. Other USGBC approved programs meeting leadership extraction criteria.

Therefore, among the given options, only Option A is relevant to the use of reused/salvaged materials or recycled content, as they can contribute to the materials reuse or recycled content criteria under Option

Question #14

Which of the following items must have safe collection, storage, and disposal for Materials and Resources Prerequisite, Storage and Collection of Recyclables?

  • A . Food waste
  • B . Medical waste
  • C . Electronic waste
  • D . Landscape waste

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

This option requires the project to provide safe collection, storage, and disposal for electronic waste, such as computers, monitors, printers, and batteries, because it contains hazardous materials that can harm human health and the environment if not handled properly1. Electronic waste can be recycled or reused by certified e-waste recyclers or manufacturers2.

References: = [LEED v4: Building Design + Construction Guide], Recycled content.

Question #15

Several Materials and Resources credits give a bonus location valuation factor, which allows products extracted, manufactured and produced within 100 mi. (161 km) of the project to take double valuation in credit calculations. The intent of this bonus is

  • A . to shorten construction duration by reducing shipping times
  • B . to avoid spreading products with potentially invasive non-native pests
  • C . to incentivize the purchase of products that support the local economy
  • D . to promote design with indigenous materials in order to maintain local aesthetic quality

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The bonus location valuation factor in several Materials and Resources credits under LEED AP BD+C V4 is intended to incentivize the purchase of products that support the local economy. Products extracted, manufactured, and produced within 100 miles (161 km) of the project are valued at 200% of their cost within the calculations1.This adds value to locally produced products and materials2.

References:

LEED Quiz 8: Ch. 9 Materials & Resources Flashcards | Quizlet

LEED 2009 vs. LEED v4: Regional Materials – LaForce, LLC

Question #16

Selecting a high-reflectance interior paint which is compliant with South Coast Air Quality Management District (SCAQMD) Rule 1113 can help contribute towards which two credits?

  • A . Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Interior Lighting
  • B . Indoor Environmental Quality Credit, Low-Emitting Materials and Sustainable Sites Credit, Site Assessment
  • C . Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Minimum Indoor Environmental Quality Performance
  • D . Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies and Indoor Environmental Quality Prerequisite, Minimum Indoor Environmental Quality Performance

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

Selecting a high-reflectance interior paint that meets the SCAQMD Rule 1113 can help contribute towards two credits: Indoor Environmental Quality Credit, Low-Emitting Materials and Indoor Environmental Quality Credit, Interior Lighting. The first credit requires that interior paints and coatings comply with the VOC content limits specified by the SCAQMD Rule 1113 or equivalent standards to reduce indoor air contaminants that are odorous, irritating, and/or harmful to the comfort and well-being of installers and occupants1The second credit aims to provide high-quality lighting that supports visual acuity and occupant comfort, and that responds to the needs of the space and its users. One of the strategies to achieve this credit is to use light-colored finishes with a minimum reflectance of 0.7 for ceilings, 0.5 for walls, and 0.2 for floors to increase the effectiveness of daylighting and electric lighting systems2References:1: LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Low-Emitting Materials, page 692.2: LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Interior Lighting, page 715.

Question #17

A project team is using the whole building simulation model to quantify the percentage of energy savings for the project.

Which of the following should remain the same for both the baseline building and the proposed building?

  • A . Building operating schedule and occupancy hours
  • B . Building operating schedule and total window area
  • C . Building envelope construction and occupancy hours
  • D . Total window area and building envelope construction

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

This option requires the project team to use the same building operating schedule and occupancy hours for both the baseline building and the proposed building in the whole building simulation model1. This option ensures that the energy savings are calculated based on the same level of building activity and occupancy, which are major factors that affect the energy performance of a building2.

References: = LEED v4: Building Design + Construction Guide, [Whole Building Energy Simulation – an overview | ScienceDirect Topics].

Question #18

For a task chair purchased for a healthcare facility, which portion of the product contributes toward Materials and Resources Credit, Furniture and Medical Furnishings?

  • A . Wheels, 4% of product by weight, that do not contain lead, mercury, cadmium or antimony
  • B . Fabric, 5% of product by weight, with stain resistant treatment containing Perfluorinated Compounds (PFCs)
  • C . Metal base, 20% of product by weight, which do not contain heavy metals and is not plated with hexavalent chromium
  • D . Plastic armrests, 30% of product by weight, with added antimicrobial treatment

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The metal base, 20% of product by weight, which do not contain heavy metals and is not plated with hexavalent chromium, contributes toward Materials and Resources Credit, Furniture and Medical Furnishings. This is because it meets the criteria of Option 1: Minimal Chemical Content, which requires that all components that constitute at least 5%, by weight, of a furniture or medical furnishing assembly must contain less than 100 ppm of at least four of the five chemical groups listed in the option. The other portions of the product either do not meet the 5% weight threshold (wheels), or contain chemicals that are restricted by Option 1 (fabric, armrests). References: LEED v4 BD+C Reference Guide, Materials and Resources Category, MRc Furniture and Medical Furnishings, Option 1. Minimal Chemical Content, page 711.

Question #19

Which principal areas must the LEED AP focus on to attain the Integrative Process Credit, Integrative Process?

  • A . Materials and resources
  • B . Location and site selection
  • C . Regional priority and innovation
  • D . Energy and water related systems

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

The Integrative Process credit, Integrative Process, requires the project team to conduct a preliminary analysis of the energy and water related systems during the pre-design phase, and use the results to inform the design and construction of the project. The analysis must include at least two potential strategies for each of the following areas: site conditions, massing and orientation, basic envelope attributes, lighting levels, thermal comfort ranges, plug and process load needs, programmatic and operational parameters, outdoor water use, and indoor water use. The project team must also document how the analysis informed the owner’s project requirements, basis of design, and design documents.

References:

LEED v4 Reference Guide for Building Design and Construction, Integrative Process Credit: Integrative Process, page 811

Integrative Process Worksheet2

Question #20

A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%.

Which alternative analyses should the team run to check different impact measurements?

  • A . Change the orientation of the design case building
  • B . Optimize the slab depth of the design case building
  • C . Decrease the gross floor area of the baseline building
  • D . Increase the wall mass and types of windows in the baseline building

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

This alternative analysis can help the team check the impact of reducing the amount of concrete used in the building, which can affect several impact categories, such as global warming potential (GWP), acidification, and eutrophication1. Concrete is a material with high embodied energy and carbon emissions, and reducing its use can lower the environmental impact of the building2. Optimizing the slab depth can also improve the thermal performance and daylighting of the building, which can reduce the operational energy use and demand3.

References: = LCA in LEED – Whole-building Life Cycle Assessment, Concrete and Embodied Carbon C Can we reduce carbon emissions and still use concrete?, Optimizing Slab Thickness for Energy Performance.

Question #21

What is the minimum number of members of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

  • A . One
  • B . Two
  • C . Four
  • D . Six

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

According to the LEED Reference Guide for Building Design and Construction1, the Integrative Process Prerequisite, Integrative Project Planning and Design, requires the project to assemble an integrated project team that includes at least four key project team members, in addition to the owner or owner’s representative. The key project team members are those who have the authority and responsibility to make design decisions and implement them during construction. The integrated project team should include professionals from different disciplines, such as architecture, engineering, landscape, interior design, construction, commissioning, operations, and maintenance. The integrated project team should collaborate throughout the project phases, from discovery to occupancy, to achieve the project goals and optimize the building performance.

References:

LEED Reference Guide for Building Design and Construction v4

Integrated Product Team (IPT) – AcqNotes

The Power of an Integrated Project Team Process – Little

Question #22

A project in a cold climate does not want a highly reflective roof because they want the heat absorption.

How can this project comply with Sustainable Sites Credit, Heat Island Reduction?

  • A . The credit is not feasible for this project
  • B . The credit may be achieved by using nonroof measures only
  • C . The credit is applicable for projects that document this special condition
  • D .   The credit can only be achieved by using an alternative compliance path

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

The credit may be achieved by using nonroof measures only, such as shading, paving, and vegetation, to reduce the heat island effect on the site. The credit does not require a highly reflective roof for all projects, but allows for flexibility and trade-offs depending on the climate and design conditions. The project can use the Heat Island Reduction1to demonstrate compliance with the credit requirements. The credit is feasible and applicable for this project, and does not need an alternative compliance path.

References: SS Credit Heat Island Reduction, LEED v4 Reference Guide for Building Design and Construction234

Question #23

Discussing the project goals to help identify the credits and options that the team should attempt is an example of

  • A . documenting LEED credits
  • B . creating the Basis of Design (BOD)
  • C . developing the LEED Scorecard
  • D . implementing the Commissioning (Cx) Plan

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Discussing the project goals to help identify the credits and options that the team should attempt is an example of developing the LEED Scorecard. The LEED Scorecard is a tool that shows the potential points that a project can achieve under each credit category of the LEED rating system1.Developing the LEED Scorecard involves selecting the most appropriate credits and options based on the project’s goals, location, budget, and design2. The scorecard helps the project team track their progress and prioritize their actions throughout the design and construction process1.

References:

LEED scorecard | U.S. Green Building Council

LEED v4: Building Design + Construction Guide – U.S. Green Building Council

Question #24

A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution.

Which of the following suggestions should the LEED AP give to the project owner?

  • A . Modify the design to enclose the performance areas
  • B . Calculate the return on investment over the 20-year life of the project
  • C . Compare the energy consumption against an alternative
  • D . Inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

The Sustainable Sites Credit, Light Pollution Reduction aims to minimize the adverse effects of artificial lighting on the night sky, human health, and wildlife1. However, the credit does not apply to lighting that is required for safety, security, or emergency purposes2. According to the LEED Reference Guide for Building Design and Construction, lighting for theatrical performances is considered an emergency purpose and is exempt from the credit requirements3. Therefore, the LEED AP should inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction and does not need to be modified or compared to an alternative. Enclosing the performance areas would not reduce light pollution, but rather increase energy consumption and affect the outdoor experience. Calculating the return on investment over the 20-year life of the project is irrelevant to the credit and would not help achieve it.

References:

Light Pollution Reduction

Light Pollution Reduction: Sustainable Site Credit for LEED Existing Building O+M

[LEED Reference Guide for Building Design and Construction v4], page 581

Question #25

Which of the following groups of documents is most likely to support both Indoor Environmental Quality Credit, Thermal Comfort, and Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control?

  • A . Architectural floor plans, mechanical plans, lighting plans
  • B . Photometric plans, mechanical schedules, lamp specifications
  • C . Lighting plans, surveys of occupants, sequence of operations
  • D . Surveys of occupants, photometric plans, mechanical schedules

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The most likely group of documents to support both Indoor Environmental Quality Credit, Thermal Comfort, and Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control is C, lighting plans, surveys of occupants, sequence of operations.

Lighting plans show the layout and type of lighting fixtures, as well as the lighting controls, such as dimmers, timers, occupancy sensors, or daylight sensors. Surveys of occupants provide feedback on the satisfaction and comfort level of the building users regarding the thermal and lighting conditions. Sequence of operations describes how the mechanical and lighting systems operate and respond to different scenarios, such as occupancy, temperature, or daylight levels.

These documents can demonstrate that the project meets the requirements for both credits, which are:

– For Thermal Comfort, the project must design the HVAC systems and the building envelope to meet the requirements of ASHRAE Standard 55-2010, Thermal Environmental Conditions for Human Occupancy, or a local equivalent, and provide individual thermal comfort controls for at least 50% of the individual occupant spaces, and group thermal comfort controls for all shared multi-occupant spaces1.

– For Interior Lighting, Option 1.Lighting Control, the project must provide individual lighting controls that enable adjustments to suit individual task needs for at least 90% of the individual occupant spaces, and provide lighting system controls for all shared multi-occupant spaces that allow occupants to adjust the lighting to meet group needs and preferences2.

The other groups of documents are less likely to support both credits, because:

– Architectural floor plans, mechanical plans, and lamp specifications do not show the lighting controls or the occupant feedback.

– Photometric plans, mechanical schedules, and lamp specifications do not show the thermal comfort design or the occupant feedback.

– Surveys of occupants, photometric plans, and mechanical schedules do not show the lighting controls or the thermal comfort design.

References: LEED v4: Building Design + Construction Guide, Indoor Environmental Quality Credit, Thermal Comfort, Requirements1; LEED v4: Building Design + Construction Guide, Indoor Environmental Quality Credit, Interior Lighting, Option 1.Lighting Control, Requirements2

Question #26

When the project occupancy is not known, which method is recommended?

  • A . Default occupant density from ASHRAE 62.1-2010, Table 6-1
  • B . Default occupant density from ASHRAE 90.1-2010, Table G3.1.1A
  • C . Weekly average taken into account all the occupants in a typical 24-hour day of operation
  • D . Occupancy measured for eight hours, between 8 a.m. and 5 p.m., for all occupancy patterns

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

This method is recommended when the project occupancy is not known, because it provides the default occupant density values for various space types, such as offices, classrooms, retail, and restaurants1. These values are based on the typical or average occupancy of similar spaces, and can be used to estimate the ventilation requirements and energy performance of the project2.

References: = LEED v4: Building Design + Construction Guide, ASHRAE 62.1-2010, Table 6-1.

Question #27

In order to meet the minimum qualifications for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification a Commissioning (Cx) agent must have completed the commissioning process activities for a minimum of how many similar projects?

  • A . Zero
  • B . One
  • C . Two
  • D . Three

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The commissioning (Cx) agent must have completed the commissioning process activities for a minimum of two similar projects in order to meet the minimum qualifications for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. This is stated in the LEED v4 Building Design + Construction Guide, under the section “Energy and Atmosphere Credits Overview”. The guide also provides examples of similar projects that can be used as references for commissioning.

References: [LEED v4: Building Design + Construction Guide], Fundamental commissioning and verification – U.S. Green Building Council, EA Energy & Atmosphere Overview – Lawrence Berkeley National Laboratory, Fundamental Commissioning and Verification C Above Green, EAp1: Fundamental Commissioning and Verification C Above Green, LEED credit library | U.S. Green Building Council

Question #28

A Healthcare Project is constructing a new building adjacent to an existing LEED Certified hospital facility. The new building’s location is on the same hospital campus as the certified facility. The entire hospital campus was analyzed with an Environmental Site Assessment (ESA) as part of the certified facility’s project scope.

The new building project needs to complete a new Phase I ESA if

  • A . the Phase II ESA uncovers suspected contamination
  • B . contamination was identified by the certified facility
  • C . the certified facility’s Phase I ESA is older than 180 days
  • D . the local equivalent standard is more stringent than ASTM E1527-05

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

the local equivalent standard is more stringent than ASTM E1527-05

According to the LEED v4 Reference Guide for Building Design and Construction, a Phase I ESA is required for all projects, except for those located on previously developed land that has not been used for industrial, commercial, or agricultural purposes. The Phase I ESA must follow the ASTM E1527-05 standard or a local equivalent. However, if the local equivalent is more stringent than the ASTM standard, then the projectmust comply with the local equivalent. Therefore, if the new building project is located in a jurisdiction that has a more rigorous standard for Phase I ESA than ASTM E1527-05, then it must complete a new Phase I ESA, regardless of the previous ESA done for the certified facility.

References:

Reference Guide for Building Design and Construction v4 C Pages 81-821

LEED v4: Building Design + Construction Guide – U.S.Green Building Council2

Question #29

The total land area within a 1/4 mi. (0.40 km) radius of a project boundary consists of 130 acres (53 hectares) and has a residential to nonresidential ratio of 60:40. Within this same total land area, there are 780 dwelling units and1,600,000 ft2 (148 645 m2) of nonresidential building space.

Given these parameters, what are the surrounding residential and nonresidential densities when attempting to achieve Location and Transportation Credit, Surrounding Density and Diverse Uses?

  • A . 10 dwelling units per acre (24 dwelling units per hectare) and a Floor Area Ratio (FAR) of 0.47
  • B . 10 dwelling units per acre (24 dwelling units per hectare) and a FAR of 0.70
  • C . 13 dwelling units per acre (32 dwelling units per hectare) and a FAR of 0.47
  • D . 15 dwelling units per acre (36 dwelling units per hectare) and a FAR of 0.70

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The surrounding residential density is calculated by dividing the total number of dwelling units by the total residential land area. In this case, it would be 780 dwelling units divided by 60% of 130 acres, which equals approximately 13 dwelling units per acre (or 32 dwelling units per hectare).

The nonresidential density, or Floor Area Ratio (FAR), is calculated by dividing the total nonresidential building floor area by the total nonresidential land area. In this case, it would be 1,600,000 ft² divided by 40% of 130 acres, which equals a FAR of approximately 0.47.

These calculations are used when attempting to achieve the Location and Transportation Credit, Surrounding Density and Diverse Uses, under the LEED AP BD+C V4 rating system.

References:

[LEED v4 BD+C Reference Guide]

Question #30

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

  • A . Owner
  • B . Contractor
  • C . Occupants
  • D . Facility manager

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

Contractor

The contractor is the project team member who should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. The contractor is responsible for implementing the waste management plan, which includes estimating the types and quantities of waste materials, identifying the diversion strategies, selecting the waste haulers and recyclers, tracking and documenting the waste diversion performance, and training the subcontractors and workers. The contractor can provide valuable input on how to reduce, reuse, and recycle the construction and demolition waste, as well as identify potential challenges and opportunities for achieving the prerequisite requirements.

References:

Reference Guide for Building Design and Construction v4 C Pages 263-2641

LEED Certification and Sustainable Construction Waste Management1

Question #31

In the calculations for Water Efficiency Credit, Outdoor Water Use Reduction, food gardens

  • A . must be calculated using at least 20% from an alternative water source
  • B . must be calculated using 100% potable water
  • C . may be included or excluded from the calculations
  • D . may be calculated using a standard 20% reduction from baseline

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Food gardens may be included or excluded from the calculations for Water Efficiency Credit, Outdoor Water Use Reduction, as per the project team’s discretion. If included, food gardens must be calculated using 100% potable water. If excluded, food gardens must be irrigated with 100% captured rainwater, recycled graywater, or water treated and conveyed by a public agency specifically for nonpotable uses.

References:

Outdoor Water Use Reduction credit in LEED BD+C: New Construction v4.1 – LEED v4.11 LEED v4 BD+C WE Guide2

Question #32

A luxury hotel project is in the design phase and is located on a scenic waterfront. It is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies.

Which of the following credits would be desirable considering the location of the project?

  • A . Energy and Atmosphere Credit, Optimize Energy Performance, Exemplary Performance
  • B . Indoor Environmental Quality Credit, Quality Views, Exemplary Performance
  • C . Indoor Environmental Quality Credit, Acoustic Performance, Exemplary Performance
  • D . Energy and Atmosphere Credit, Enhanced Commissioning, Exemplary Performance

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

The LEED Platinum certification requires the project to achieve exemplary performance in at least one credit that allows it, as specified in the LEED Reference Guide1. One of the credits that meets this criterion is the Indoor Environmental Quality Credit, which focuses on providing healthy and comfortable indoor environments for occupants. The credit has two options: Quality Views and Enhanced Commissioning. Quality Views requires the project to have windows that provide views of natural scenery or water bodies, which can enhance the well-being and satisfaction of occupants. Enhanced Commissioning requires the project to have a comprehensive commissioning plan that ensures all systems are properly installed, tested, and operated before occupancy. Both options can help reduce energy consumption, improve indoor air quality, and create a positive sensory experience for occupants.

References:

LEED Reference Guide v4

LEED Platinum Certification – LD Products

LEED Accreditation | LEED Certification & Credentials Overview – GBES

Question #33

What supporting material is required for all LEED Building Design and Construction projects in order to document Location and Transportation Credit, Bicycle Facilities for the bicycle network?

  • A . Photographs of bicycle network signage and directional signposts
  • B . Photographs of the installed bicycle storage and shower facilities
  • C . Vicinity map showing bicycle network, route and distance along network to eligible destination(s)
  • D . Manufacturer specifications for the chosen bicycle storage facilities, including the number of bicycles supported by each bike rack

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The Location and Transportation Credit, Bicycle Facilities, requires the project team to provide a vicinity map that shows the bicycle network, the route and the distance along the network to eligible destination(s) for all LEED Building Design and Construction projects. The vicinity map is a supporting material that demonstrates that the project site is within a 200-yard (180-meter) walking distance of a bicycle network that connects to at least one of the following: diverse uses, public transportation, recreation facilities, or schools1. The vicinity map must also show the scale and the north arrow, and indicate the project site and the eligible destination(s)2. The photographs of bicycle network signage and directional signposts, the photographs of the installed bicycle storage and shower facilities, and the manufacturer specifications for the chosen bicycle storage facilities are not required for the bicycle network, but for the bicycle storage and shower facilities.

References:

• LEED v4 Reference Guide for Building Design and Construction, Location and Transportation Credit:

Bicycle Facilities, page 1281

• LEED v4.1 Bicycle Storage Requirements

Question #34

Which of the following will result in a higher demand for potable water use in irrigation?

  • A . Sparsely planted area
  • B . Drip irrigation system
  • C . High evapotranspiration rate
  • D . Rainwater harvesting system

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The answer is C. A high evapotranspiration rate will result in a higher demand for potable water use in irrigation. Evapotranspiration is the process by which water is transferred from the land to the atmosphere by evaporation from the soil and other surfaces and by transpiration from plants. The higher the evapotranspiration rate, the more water is lost from the soil and plants, and the more irrigation is needed to replenish the moisture. The other options will not increase the demand for potable water use in irrigation. A sparsely planted area will have less vegetation and less transpiration, reducing the water demand. A drip irrigation system will deliver water directly to the plant roots, minimizing evaporation and runoff, and saving water. A rainwater harvesting system will collect and store rainwater for irrigation, reducing the reliance on potable water sources. For more information on outdoor water use reduction and irrigation efficiency, you can refer to the LEED v4 Reference Guide for Building Design and Construction1or the Water Sense Water Budget Tool2.

Question #35

What is the minimum gross floor area required for a Building Design and Construction project to be eligible for certification?

  • A . 250 ft2 (23 m2)
  • B . 500 ft2 (46 m2)
  • C . 750 ft2 (70 m2)
  • D . 1000 ft2 (93 m2)

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED minimum program requirements, the LEED project must include a minimum of 1000 square feet (93 square meters) of gross floor area for the LEED BD+C and LEED O+M rating systems1.

References:

LEED v4: Building Design + Construction Guide

LEED minimum program requirements

Question #36

When preparing the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, the Construction General Permit must contain which of the following?

  • A . Waste Management Plan
  • B . Building orientation on the site
  • C . Installation plan for perimeter control
  • D . Minimum standards for equipment exhaust

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The Construction General Permit (CGP) for the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, must contain an installation plan for perimeter control. This is part of the Erosion and Sedimentation Control (ESC) Plan, which is designed to prevent loss of soil during construction by stormwater runoff and/or wind erosion, prevent sedimentation of storm sewer or receiving streams, and prevent polluting the air with dust and particulate matter1.

References:

Sustainable Sites Prerequisites | GlobalSpec

Question #37

A comprehensive rainwater management plan may include design elements such as

  • A . artificial turf, bioretention pond, cisterns and hay bales
  • B . cisterns, porous pavement, swales and vegetated roofs
  • C . soil compaction, swales, vegetated roofs and xeriscaping
  • D . bioretention pond, cisterns, porous pavement and stabilized construction entrance

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

These design elements are examples of low-impact development (LID) and green infrastructure (GI) practices that can reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site1. Cisterns can collect and store rainwater for reuse or infiltration, porous pavement can allow water to seep into the ground, swales can convey and filter stormwater runoff, and vegetated roofs can reduce runoff and evapotranspiration2.

References: = LEED v4: Building Design + Construction Guide, Achieving SSc Rainwater Management in LEED v4.1.

Question #38

During preliminary energy analysis, what energy reduction strategies can best help in reducing the energy load in the new building construction project?

  • A . Green roof
  • B . Site conditions
  • C . Massing and orientation
  • D . Programmatic and operational parameters

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

During preliminary energy analysis, massing and orientation are energy reduction strategies that can best help in reducing the energy load in the new building construction project. Massing and orientation refer to the shape, size, and direction of the building, which affect the amount of solar heat gain, daylight, and natural ventilation that the building receives. By analyzing the massing and orientation of the building, the project team can optimize the design to minimize the heating, cooling, and lighting energy demand, and enhance the thermal comfort and indoor environmental quality of the building. The LEED v4 Reference Guide for Building Design and Construction states that "the project team should use the results of the analysis to inform the owner’s project requirements, basis of design, and design documents"1. The other options, such as green roof, site conditions, and programmatic and operational parameters, are not energy reduction strategies, but factors that influence the energy performance and demand of the building.

References:

• LEED v4 Reference Guide for Building Design and Construction, Integrative Process Credit: Integrative Process, page 811

• Integrative Process Worksheet2

Question #39

For schools intended for grades eight and below (or ages 14 and below), which of the following scenarios would demonstrate compliance with Location and Transportation Credit, Access to Quality Transit, Schools, Option 2. Pedestrian Access?

  • A . 30% of the students live no more than a 3/4 mi. (1.20 km) walking distance from a functional entry of a school building
  • B . 50% of the students live no more than a 3/4 mi. (1.20 km) walking distance from a functional entry of a school building
  • C . 30% of the students live no more than a 1 1/2 mi. (2.40 km) walking distance from a functional entry of a school building
  • D . 50% of the students live no more than a 1 1/2 mi. (2.40 km) walking distance from a functional entry of a school building

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

For schools intended for grades eight and below (or ages 14 and below), Option 2. Pedestrian Access requires that at least 50% of the students live no more than a 3/4 mi. (1.20 km) walking distance from a functional entry of a school building. This option aims to encourage schools to locate in areas where students can walk or bike to school, reducing vehicle trips and emissions, and promoting physical activity and health. Option 2 is available only for projects that do not meet the requirements of Option 1. Transit-Served Location, which requires access to quality transit service within a 1/4 mi. (400 m) walking distance for at least 50% of the students.

References:

Access to Quality Transit credit in LEED BD+C: Schools v4 – LEED v41

LEED Certification- Requirements for LT CREDIT: ACCESS TO QUALITY TRANSIT2

Understanding the LEED BD+C: Location and Transport credit3

Question #40

A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development – Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of

  • A . 12,500 ft2 (1 160 m2)
  • B . 15,000 ft2 (1 400 m2)
  • C . 25,000 ft2 (2 300 m2)
  • D . 35,000 ft2 (3 250 m2)

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

According to the LEED v4 Reference Guide for Building Design and Construction, Option 1 of the Site Development – Protect or Restore Habitat credit requires restoring 25% of the site area (including the building footprint) with native or adapted vegetation1.To achieve exemplary performance, the project must double the credit requirements and restore 50% of the site area2. In this case, the site area is 100,000 ft2 (9 290 m2), so the project must restore 50,000 ft2 (4 645 m2) with vegetation. The project already has 35,000 ft2 (3 250 m2) of native vegetated open space, so it needs to add another 15,000 ft2 (1 395 m2) of vegetation. Since the on-grade surface is fully occupied by the building footprint and the asphalt parking, the only option is to incorporate a vegetated roof. Therefore, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of 15,000 ft2 (1 395 m2).

References: SS Credit Site Development – Protect or Restore Habitat, LEED v4 Reference Guide for Building Design and Construction13

Question #41

What is a benefit of including the public in a charrette for a new school before the pre-design phase?

  • A . Neighbors can plan for future construction
  • B . It will help streamline the permitting process
  • C . Potential partnerships with the community can be revealed
  • D . The owner can determine financial strategies based on the public’s input

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

A charrette is a collaborative design process that involves multiple stakeholders, such as the owner, the design team, the community, and the users. By including the public in a charrette for a new school before the pre-design phase, potential partnerships with the community can be revealed. For example, the school might share facilities or resources with a nearby library, park, or community center. This can enhance the social and environmental benefits of the project, as well as reduce costs and increase efficiency.

References: LEED BD+C Reference Guide, Introduction, page 171; LEED BD+C Reference Guide, Integrative Process, page 291

Question #42

The material cost for a project is $100,000.

What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?

  • A . $10,000
  • B . $12,500
  • C . $22,500
  • D . $25,000

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4 Reference Guide for Building Design and Construction, Option 2 of the Sourcing of Raw Materials credit requires using products that meet at least one of the responsible extraction criteria for at least 25%, by cost, of the total value of permanently installed building products in the project1. Therefore, for a project with a material cost of $100,000, the minimum material value needed to achieve this option is 25% of $100,000, which is $25,000.

Question #43

What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

  • A . Energy and Atmosphere Credit, Demand Response
  • B . Energy and Atmosphere Credit, Advanced Energy Metering
  • C . Energy and Atmosphere Credit, Building Level Energy Metering
  • D . Energy and Atmosphere Credit, Green Power and Carbon Offsets

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

The Energy and Atmosphere Credit, Demand Response rewards projects that participate in demand response programs that aim to reduce peak electricity demand and shift the load to off-peak periods. The LEED v4 Reference Guide for Building Design and Construction states that "the intent of this credit is to increase participation in demand response technologies and programs that make energy generation and distribution systems more efficient, increase grid reliability, and reduce greenhouse gas emissions"1. The project team must either implement a permanent demand response program or develop a plan to implement a program within a year of occupancy. The project team must also demonstrate that the building has the capability to reduce its peak electricity demand by at least 10% in response to demand response signals.

References:

LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Credit:

Demand Response, page 2721

Demand response | U.S. Green Building Council2

Question #44

A newly constructed school has installed solar thermal systems and wind turbines on site. To achieve the maximum number of Energy and Atmosphere points, which team members must be included?

  • A . Energy Modeler and Contractor
  • B . Construction Manager and Energy Modeler
  • C . Energy Modeler and Commissioning (Cx) Agent
  • D . Commissioning (Cx) Agent and Facilities Manager

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

To achieve the maximum number of Energy and Atmosphere points, the project team must include an energy modeler and a commissioning agent. The energy modeler is responsible for performing the whole-building energy simulation that demonstrates the energy performance improvement over the baseline building, which is required for Energy and Atmosphere Prerequisite 2 and Credit 11. The commissioning agent is responsible for verifying that the building’s energy systems are installed, calibrated, and perform according to the owner’s project requirements, basis of design, and construction documents, which is required for Energy and Atmosphere Prerequisite 1 and Credit 31. The commissioning agent also ensures that the renewable energy systems are properly integrated and functioning2. The contractor and the construction manager are not directly involved in the energy modeling or commissioning process, although they must follow the design specifications and coordinate with the commissioning agent. The facilities manager is not required for achieving the Energy and Atmosphere points, although they may benefit from the training and documentation provided by the commissioning agent.

References:

LEED v4 for Building Design and Construction, p.361

Understanding Integrative Design in LEED v4, p.92

Question #45

Which of the following buildings meets the Minimum Program Requirements for LEED certification?

  • A . A 1,500 ft2 (139 m2) Tourism Center located on a previously undeveloped one-acre site
  • B . A 20,000 ft2 (1 859 m2) Transit Parking Garage located on a previously developed five-acre site
  • C . A 2,500 ft2 (232 m2) mobile Health Clinic located on a previously constructed above-water dock
  • D . A 5,000 ft2 (465 m2) Science Education center on an above-water pier that is being built specifically for the Education center

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

The Minimum Program Requirements (MPRs) for LEED certification are:

MPR 1: Must be in a permanent location on existing land

MPR 2: Must use reasonable LEED boundaries

MPR 3: Must comply with project size requirements

Option A does not meet MPR 1 because it is located on a previously undeveloped site, which is not considered existing land. Option B does not meet MPR 3 because it is a parking garage, which is excluded from LEED certification unless it is part of a larger project. Option C does not meet MPR 1 because it is a mobile clinic, which is not considered permanent. Option D meets all the MPRs because it is a permanent building on existing land, it has reasonable LEED boundaries, and it meets the minimum gross floor area of 1,000 ft2 (93 m2) for BD+C projects.

References:

LEED minimum program requirements

Minimum Program Requirements (MPRs)

What do the LEED Minimum Program Requirements Really Mean?

Question #46

Which views would qualify as a quality view for Indoor Environmental Quality Credit, Quality Views?

  • A . A,B,C
  • B . B,C,D
  • C . C,D,E
  • D . A,B,D

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Quality views are defined in LEED as those which consist of multiple elements of nature, weather, or movement that allow for a connection beyond the interior space. Views that allow a clear line of sight to the exterior via vision glazing, with a view factor of 3 or greater, qualify for this credit. Fixed glazing in common spaces can also contribute to this credit.

References: This information is a synthesis based on the criteria for ‘Indoor Environmental Quality Credit, Quality Views’ from the LEED BD+C Reference Guide available on the USGBC website. For a detailed explanation, please refer to the specific credit requirements in the LEED BD+C Reference Guide.

Question #47

Which of the following innovation proposals is most likely to be successful to achieve an Innovation Credit?

  • A . Providing an educational program on the environmental and human health benefits of green building practices
  • B . Including locked, indoor bicycle storage for 100% of project occupants
  • C . Being located next to a 20 mi. (32 km) award-winning bicycle trail
  • D . Distributing leaflets to project occupants about available public transit services nearby

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

Providing an educational program on the environmental and human health benefits of green building practices is a potential innovation strategy that is not addressed by any existing LEED credit. It also meets the criteria of being measurable, replicable, and having a positive impact on the project and the environment.

References: LEED v4 BD+C Reference Guide, Innovation Category, INc1: Innovation, Option 1. Innovation (1 point), page 704.

Question #48

For Energy and Atmosphere Credit, Advanced Energy Metering, what is the minimum amount of time that the metering system should store data?

  • A .   6 months
  • B . 12 months
  • C . 24 months
  • D . 36 months

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

For Energy and Atmosphere Credit, Advanced Energy Metering, the minimum amount of time that the metering system should store data is36 months. This is to ensure that the data can be used for long-term analysis and verification of energy performance1. The credit also requires that the metering system be capable of transmitting data to a remote location and reporting energy use at least hourly1.

References: Advanced energy metering

Question #49

When working on a renovation project, asbestos containing materials have been found on the perimeter walls. When calculating the percentage of building being reused under the Materials and Resources Credit, Building Life-Cycle Impact Reduction, the materials remediated will be

  • A . included in the calculation
  • B . excluded from the calculation
  • C . excluded if the total volume is less than 25% of the building being reused
  • D . excluded if the total volume is more than 25% of the building being reused

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

The Materials and Resources Credit, Building Life-Cycle Impact Reduction, rewards projects that reuse existing building structures and envelopes, or salvage materials from off-site or on-site sources. According to the LEED v4 Reference Guide for Building Design and Construction, the project team must calculate the percentage of building being reused by dividing the area of the existing building structure and envelope that is reused by the total area of the completed building structure and envelope1. However, the project team must exclude from the calculation any hazardous materials that are remediated as a part of the project, such as asbestos, lead, mold, or PCBs1. Therefore, the asbestos containing materials found on the perimeter walls will be excluded from the calculation, regardless of the volume.

References:

• LEED v4 Reference Guide for Building Design and Construction, Materials and Resources Credit: Building

Life-Cycle Impact Reduction, page 5451

• Building life-cycle impact reduction | U.S. Green Building Council2

Question #50

Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 1. Surrounding Density requires project teams to exclude what type of land area from the calculations?

  • A . Buildable land within 1/4 mi. (0.40 km) of the project boundary
  • B . Public right-of-way areas within 1/4 mi. (0.40 km) of the project boundary
  • C . Surface parking areas within 1/2 mi. (0.80 km) of the project boundary
  • D . University campus land areas within 1/2 mi. (0.80 km) of the project boundary

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

This option requires the project team to exclude public right-of-way areas, such as streets, sidewalks, and alleys, from the calculations of the surrounding existing density1. This option ensures that the density is measured based on the buildable land area, which is the area available for development or construction2.

References: = [LEED v4: Building Design + Construction Guide], Surrounding density and diverse uses.

Question #51

An existing vacant office building will be completely renovated and new mechanical, electrical and plumbing systems will be installed. 20% of the building’s gross floor area will be complete at the time of certification. There will be a data center and some retail stores on the ground floor of the building at a future date.

Which rating system is applicable for the building?

  • A . LEED BD+C: Retail
  • B . LEED BD+C: Data Centers
  • C . LEED BD+C: Core & Shell Development
  • D . LEED BD+C: New Construction & Major Renovation

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

This rating system is suitable for projects where the developer controls the design and construction of the entire core and shell base building, but has no control over the design and construction of the tenant fit-out. Since the building will have a data center and retail stores in the future, but these are not the primary function

of the entire building, LEED BD+C: Core & Shell is more appropriate than LEED BD+C: Data Centers or LEED BD+C: Retail.

References: = LEED rating system selection guidance, LEED v4: Building Design + Construction Guide

Question #52

Plug-in task lighting will be utilized in a LEED project at all workstations. The task lighting is not included in the installed lighting power calculations for Energy and Atmosphere Prerequisite, Minimum Energy Performance since

  • A . it is being covered by Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control
  • B . it is specifically exempted by ASHRAE
  • C . it will be installed by the owner
  • D . the lamp wattage has not been determined

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Plug-in task lighting is considered as furniture and is not included in the installed lighting power calculations for Energy and Atmosphere Prerequisite, Minimum Energy Performance. It is also not required to comply with the lighting control requirements of ASHRAE 90.1-2010. However, it can be used to satisfy the individual control requirement of Indoor Environmental Quality Credit, Interior Lighting, Option 1.

References:

LEED v4 for Building Design and Construction, p.361

LEED v4 for Building Design and Construction, p.6012

ASHRAE 90.1-2010, Section 9.1.13

Question #53

A building owner in an arid climate is trying to design an outdoor lunch area for the tenants.

Which landscaping strategy is important to employ in order to reduce water demand?

  • A . Large maple trees for shading
  • B . Xeriscaping landscape beds
  • C . Turf grass area for picnic benches
  • D . Tropical flowers next to park benches

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

Xeriscaping is a landscaping method that reduces water demand by using plants that are adapted to dry climates, mulching the soil to retain moisture, and minimizing the amount of lawn and other turf areas. Xeriscaping can help save water, money, and energy, as well as improve the health of the soil and the environment.

References:

• How to Xeriscape for a Water-Wise Yard – Better Homes & Gardens

• Xeriscaping: how to use this landscaping method in your yard | Why subscribe?

• Xeriscaping: Gardening with Less Water – Dennis’ 7 Dees | Landscaping …

• Guide to Xeriscape Landscaping – The Spruce.

Question #54

During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value.

This strategy is an example of applying which of the following credits to the project?

  • A . Innovation Credit, Innovation
  • B . Integrative Process Credit
  • C . Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control
  • D . Materials and Resources Credit, Interiors Life-Cycle Impact Reduction

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

The Integrative Process Credit is a credit in LEED Building Design and Construction that supports high-performance, cost-effective project outcomes through an early analysis of the interrelationships among systems1. The credit requires project teams to perform analyses for both energy- and water-related systems before completing the schematic design, and to use the findings to inform the owner’s project requirements, basis of design, and design and construction documents1. The example given in the question is an illustration of how selecting a paint color with a higher light reflectance value can reduce the energy use and cost of lighting fixtures, which is an energy-related system. This strategy shows how the project team applied an integrative process to evaluate the impacts of different design options on the building performance and environmental benefits. Therefore, the correct answer is B. Integrative Process Credit.

References: Integrative Process

Question #55

The LEED AP is leading the first design charrette for a new LEED project with the project’s owners.

What document should be used to record the project goals to be used throughout the design of the project?

  • A . Owner’s Project Requirements (OPR)
  • B . Owner’s list of wants and needs
  • C . Criteria for contractor selection
  • D . Basis of Design (BOD)

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

The Owner’s Project Requirements (OPR) is the document that should be used to record the project goals to be used throughout the design of the project. The OPR is a written document that details the ideas, concepts, and criteria that are determined by the owner to be important to the success of the project1. The OPR is developed during the pre-design phase and is used as a basis for the design team to prepare the Basis of Design (BOD), which describes how the design of the building systems meets the OPR2. The OPR is also used to evaluate the design, construction, and commissioning of the project to ensure that the owner’s expectations are met3.

References:

• LEED v4 for Building Design and Construction, p. 63

• LEED v4 for Building Design and Construction, p. 64

• SECTION 018114 – SUSTAINABLE DESIGN REQUIREMENTS – LEED v4 BD+C, p. 5

Question #56

Which of the following prerequisites or credits are affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit. Thermal Comfort?

  • A . Energy and Atmosphere Credit. Demand Response
  • B . Energy and Atmosphere Credit. Advanced Energy Metering
  • C . Energy and Atmosphere Prerequisite. Minimum Energy Performance
  • D . Energy and Atmosphere Prerequisite. Building Level Energy Metering

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Using plug-in devices can affect the energy performance of the building, which is one of the criteria for achieving Indoor Environmental Quality Credit. Thermal Comfort. The LEED v4 Reference Guide for Building Design and Construction states that "the project team must demonstrate that the proposed design meets the minimum energy performance requirements of ASHRAE Standard 90.1-2010, Appendix G, with errata"1. Plug-in devices are considered as part of the process loads in the energy model, and they can increase the energy consumption and demand of the building. Therefore, the project team must account for the plug-in devices in the energy model and ensure that the proposed design meets or exceeds the baseline performance rating.

References:

LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite: Minimum Energy Performance, page 2591

LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Thermal Comfort, page 7041

Question #57

What phase of the integrative process gives the team the greatest chance of success in meeting the project’s environmental goals cost-effectively?

  • A . Design
  • B . Discovery
  • C . Operations
  • D . Construction

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

Discovery

The discovery phase of the integrative process gives the team the greatest chance of success in meeting the project’s environmental goals cost-effectively. The discovery phase is the initial stage of the project, where the team establishes the vision, goals, and performance criteria, conducts a site assessment, identifies synergies and trade-offs among systems, and performs preliminary analysis and modeling of energy and water use1.By engaging in this phase early and iteratively, the team can explore various design options, identify potential savings and benefits, and optimize the project outcomes2.

References:

Reference Guide for Building Design and Construction v4 C Pages 28-291

Understanding Integrative Design in LEED v4 – BuildingGreen2

Question #58

A commercial office building with a footprint of 70,000 ft2 (6 503.2 m2) has an overall site area of 200,000 ft2 (18 580.6 m2). The project design includes 15,000 ft2 (1 393.5 m2) of pedestrian oriented hardscape and 18,000 ft2 (1 672.3 m2) of vegetated open space.

Which of the following is necessary to satisfy the requirement for the outdoor space to be physically accessible when calculating the Sustainable Sites Credit, Open Space?

  • A . A garden space dedicated to industrial food production for use by local communities
  • B . A garden space with only one vegetation type and species during the summer for visual interest
  • C . A dark paving area with site elements to encourage parking near wetlands or naturally designed ponds
  • D . A pedestrian-oriented paving or turf area with physical site elements that accommodate outdoor social activities

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

A pedestrian-oriented paving or turf area with physical site elements that accommodate outdoor social activities is necessary to satisfy the requirement for the outdoor space to be physically accessible when calculating the Sustainable Sites Credit, Open Space. This is because the outdoor space must be designed to encourage regular use by occupants and visitors1. A garden space dedicated to industrial food production for use by local communities may not be accessible to the building occupants and visitors2. A garden space with only one vegetation type and species during the summer for visual interest does not meet the requirement of having two or more types of vegetation or overhead vegetated canopy1. A dark paving area with site elements to encourage parking near wetlands or naturally designed ponds is not considered as pedestrian-oriented hardscape and may have negative impacts on the natural environment3.

References:

• Open Space, p. 1

• NC-v4 SSc3: Open space, p. 2

• LEED v4 for Building Design and Construction, p. 72

Question #59

Which of the following project types is required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations?

  • A . Retail
  • B . Schools
  • C . Healthcare
  • D . Core and Shell

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Healthcare projects are required to consider the perimeter floor area instead of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight calculations. This is because healthcare projects have different daylighting needs and challenges than other project types, and the perimeter area is more likely to have access to natural light and views. The perimeter floor area is defined as the regularly occupied spaces within 15 feet (4.5 meters) of the exterior wall that meets the minimum glazing requirements.

References:

LEED v4 for Building Design and Construction, p.6021

LEED v4 for Building Design and Construction, p.362

Question #60

The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced

Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification.

What is a required responsibility for the CxA to achieve the stated objective?

  • A . Verify that training requirements are completed
  • B . Develop systems manual for the commissioned systems
  • C . Review contractor submittals for the commissioned systems
  • D . Verify installation and performance of the commissioned systems

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4: Building Design + Construction Guide, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, requires the project to hire a Commissioning Authority (CxA) to oversee the commissioning process for the mechanical, electrical, plumbing, and renewable energy systems and assemblies. The CxA must have documented commissioning authority experience in at least two building projects, and must not be an employee of the design or construction firms, although they may be contracted through them. The CxA must report the results, findings, and recommendations directly to the owner1.

One of the required responsibilities for the CxA to achieve the prerequisite is to verify installation and performance of the commissioned systems. This includes conducting site observations and spot-checking of equipment installation, performing functional performance testing of the systems, verifying system performance by reviewing testing and balancing reports, and preparing a summary commissioning report of the activities and results1.

The other choices are not required responsibilities for the CxA to achieve the prerequisite, but they are additional responsibilities for the CxA to achieve the Energy and Atmosphere Credit, Enhanced Commissioning, which goes beyond the prerequisite by including more systems, more verification activities, and more documentation.

These additional responsibilities are2:

– Verify that training requirements are completed. This includes reviewing training plans, agendas, and materials, and verifying that the training delivery and documentation are completed and consistent with the owner’s project requirements (OPR).

– Develop systems manual for the commissioned systems. This includes compiling and reviewing the systems manual that provides the necessary information for operating and maintaining the commissioned systems.

– Review contractor submittals for the commissioned systems. This includes reviewing the design intent and basis of design documentation, and providing feedback on the contractor submittals related to the commissioned systems, such as shop drawings, product data, and samples.

References: LEED v4: Building Design + Construction Guide, Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, Requirements1; LEED v4: Building Design + Construction Guide, Energy and Atmosphere Credit, Enhanced Commissioning, Requirements2

Question #61

A school wants to incorporate natural daylighting in classrooms on all sides of the building.

What can the project design team explain to the school district about how this strategy will affect the operational energy cost?

  • A . Heat gain will reduce the air conditioning load
  • B . Having the lights off reduces the electricity use
  • C . Reduction in lighting fixture use reduces re-lamping
  • D .   There would be passive solar heating benefits to all of the classrooms

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

Natural daylighting can reduce the electricity use for artificial lighting, which is one of the major components of operational energy cost for buildings. By having the lights off or dimmed when sufficient daylight is available, the project can save energy and money. The other options are not necessarily true or relevant for natural daylighting. Heat gain and passive solar heating depend on the orientation, shading, and insulation of the windows, not just the amount of daylight. Reduction in lighting fixture use may reduce re-lamping, but that is not a significant factor in operational energy cost compared to electricity use.

References: EA Credit Optimize Energy Performance, EQ Credit Daylight, LEED v4 Reference Guide for Building Design and Construction123

Question #62

Which would contribute to compliance with Sustainable Sites Credit, Open Space?

  • A . A mall with an indoor atrium, featuring a reflective roof
  • B . A parking lot that serves as the location for a monthly flea market
  • C . An intensive vegetated roof, provided the building has at least a 1.0 Floor to Area Ratio (FAR)
  • D . A forested area containing nature trails, that also achieves Sustainable Sites Credit, Site Development C Protect or Restore Habitat

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4: Building Design + Construction Guide, the Sustainable Sites Credit, Open Space requires the project to provide outdoor space greater than or equal to 30% of the total site area (including building footprint). At least 25% of that outdoor space must be vegetated, have overhead vegetated canopy, or be a water body. Option A does not qualify as outdoor space, Option B is not vegetated or a water body, and Option C only applies to projects with a FAR of less than 1.0. Option D meets the requirements for both outdoor space and vegetation, and also contributes to the protection or restoration of habitat1. References: LEED v4: Building Design + Construction Guide, Sustainable Sites Credit, Open Space, Requirements1

Question #63

A decorative overhead light fixture is specified for a project that costs $1,500 USD and uses recycled water bottles as part of the diffuser shade. The shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content.

Assuming no other portions of the fixture meet sustainability criteria, what would the contributing value of the fixture be?

  • A .   $75
  • B . $150
  • C . $750
  • D . $1,500

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

This option requires the project to calculate the contributing value of the fixture by multiplying the cost of the fixture by the percentage of recycled content by weight1. Since the shades are 10% of the overall weight of the fixture and are 50% post-consumer recycled content, the contributing value of the fixture is: $1,500 x 10% x 50% = $75

References: = LEED v4: Building Design + Construction Guide, Recycled content | U.S. Green Building Council.

Question #64

For major renovation and new construction projects, the required energy and water-related system analyses should be the same except for

  • A . site conditions
  • B . massing and orientation
  • C . plug and process load needs
  • D . building envelope performance

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

For major renovation and new construction projects, the required energy and water-related system analyses should be the same except for plug and process load needs. Plug and process loads are the electrical loads that are not related to lighting, heating, ventilation, and air conditioning (HVAC)systems, such as computers, appliances, equipment, and machinery. Plug and process load needs may vary depending on the type and function of the building, and they can have a significant impact on the energy performance and demand of the building. Therefore, the project team should analyze the plug and process load needs for each project and design strategies to reduce or optimize them. The other factors, such as site conditions, massing and orientation, and building envelope performance, are common to both major renovation and new construction projects, and they should be analyzed in the same way for both types of projects.

References:

• LEED v4 Reference Guide for Building Design and Construction, Integrative Process Credit: Integrative Process, page 811

• Integrative Process Worksheet2

Question #65

The scope of analysis in Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 4.

Whole-Building Life-Cycle Assessment is a

  • A . gate-to-gate assessment
  • B . cradle-to-gate assessment
  • C . cradle-to-grave assessment
  • D . cradle-to-cradle assessment

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

The scope of analysis in Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 4. Whole-Building Life-Cycle Assessment is a cradle-to-grave assessment. This means that the life cycle assessment (LCA) covers all stages of the building’s life cycle, from the extraction of raw materials (cradle) to the disposal or reuse of the building components at the end of their service life (grave)1. The LCA must include the following life cycle stages: product stage, construction process stage, use stage, and end-of-life stage2. The LCA must also account for the environmental impacts of the building’s structure and enclosure, as well as any other building elements that are permanently attached to and share service systems with the building2.

References:

Whole building life cycle assessment through LEED v4

Building life-cycle impact reduction | U.S. Green Building Council

Question #66

Which federal agency designates Federal Renewal Community sites, which can be considered High Priority Sites for project development?

  • A . U.S. Internal Revenue Service
  • B . U.S. Department of Agriculture
  • C . U.S. Environmental Protection Agency
  • D . U.S. Department of Housing and Urban Development

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

According to the LEED v4: Building Design + Construction Guide, Federal Renewal Community sites are designated by the U.S. Internal Revenue Service (IRS) as areas that are eligible for tax incentives to encourage businesses to locate and hire residents within the community. These sites are considered High Priority Sites for project development, as they support the revitalization of economically distressed areas. The other federal agencies listed do not designate Federal Renewal Community sites. References: LEED v4: Building Design + Construction Guide, Location and Transportation Credit, High Priority Site, Requirements1; U.S. Internal Revenue Service, Renewal Communities2

Question #67

In addition to Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Materials Reuse, salvaged materials contribute to the achievement of

  • A . Materials and Resources Prerequisite, Storage and Collection of Recyclables
  • B . Materials and Resources Credit, Building Product Disclosure and Optimization – Material Ingredients
  • C . Materials and Resources Credit, Construction and Demolition Waste Management
  • D . Materials and Resources Credit, Building Product Disclosure and Optimization – Environmental Product Declarations

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Materials and Resources Credit, Construction and Demolition Waste Management

Salvaged materials are materials that have been recovered or diverted from the waste stream for reuse. They can contribute to the achievement of the Construction and Demolition Waste Management credit, which aims to reduce the amount of waste generated by construction and demolition activities and divert it from landfills and incinerators. By reusing salvaged materials, projects can reduce the demand for new materials, conserve natural resources, save energy, and lower greenhouse gas emissions. Salvaged materials can be counted as part of the total waste diverted from disposal, as long as they are not counted for the Building Life-Cycle Impact Reduction credit1.

References:

Reference Guide for Building Design and Construction v4 C Pages 263-2642

LEED Certification and Sustainable Construction Waste Management3

Question #68

The owner of a large multi-building property is seeking LEED certification. In determining the LEED project boundaries the LEED AP may include non-contiguous parcels of land if

  • A . the parcels are used for temporary uses such as parking or staging that is owned and managed by a third party
  • B . the parcels directly support or are associated with normal building operations and are accessible to the project’s occupants
  • C . the parcels are part of an existing public preservation easement or resource protection area that is directly adjacent to the LEED project boundary
  • D . the parcels are part of a land trust or conservation organization for which the LEED project provides financial support for in the Sustainable Sites Credit, Site Development Credit, Protect or Restore Habitat, Option 2. Financial Support

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

In determining the LEED project boundaries, the LEED AP may include non-contiguous parcels of land if the parcels directly support or are associated with normal building operations and are accessible to the project’s occupants. This is according to the Minimum Program Requirements (MPRs) for LEED v4.1, which state that non-contiguous parcels of land may be included within the LEED project boundary if they meet these criteria1. Facilities such as parking lots, bicycle storage, shower/changing facilities, and/or on-site renewable energy that are outside of the LEED project boundary may also be included in certain prerequisites and credits if they directly serve the LEED project and are not double-counted for other LEED projects1. The other options are not valid reasons to include non-contiguous parcels of land within the LEED project boundary. Temporary uses such as parking or staging that are owned and managed by a third party do not directly support or are associated with normal building operations of the LEED project1. Existing public preservation easements or resource protection areas that are directly adjacent to the LEED project boundary are not considered as part of the LEED project boundary, unless they are owned by the project owner or the project team has permission to use them2. Land trusts or conservation organizations for which the LEED project provides financial support are not considered as part of the LEED project boundary, unless they are located within the same EPA Level III ecoregion as the project site3.

References:

• Minimum Program Requirements (MPRs) – U.S. Green Building Council

• NC-v4.1 MPR2: Must use reasonable LEED boundaries | LEEDuser

• Site development – protect or restore habitat, p. 2

Question #69

At the time of registering a project in LEED Online, Regional Priority credits are determined based upon the project’s

  • A . environmental zone
  • B . longitude and latitude
  • C . ASHRAE 90.1 – 2010 climate zone
  • D . Environmental Protection Agency Phase I Assessment

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

At the time of registering a project in LEED Online, Regional Priority credits are determined based on the project’s longitude and latitude. Regional Priority credits are bonus points that reward projects for addressing the environmental, social, and public health issues that are most relevant to their location1. The project team must enter the project’s address and confirm the precise location using the Google Maps interface in LEED Online2. The longitude and latitude coordinates are then used to identify the Regional Priority credits that are applicable to the project2. The project can earn up to four Regional Priority points by achieving the base credits that correspond to the Regional Priority credits1.

References:

Regional priority credit lookup | U.S. Green Building Council

Regional Priority (RP) credits C U.S. Green Building Council

Question #70

A commercial new construction project consists of mixed space usage. When deciding which LEED rating system to use, the LEED AP should follow which of the following rules?

  • A . If a rating system is appropriate for less than 50% of the gross area of the LEED project space then the rating system must not be used
  • B . If a rating system is appropriate for more than 50% of the gross floor area of LEED project space, then that rating system must be used
  • C . If a rating system is appropriate for 30% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable
  • D . If a rating system is appropriate for 40% to 60% of the gross floor area, the project team must independently assess their situation and decide which rating system is most applicable

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4: Building Design + Construction Guide, the 40/60 rule provides guidance for making a decision when several rating systems appear to be appropriate for a project. To use this rule, first assign a rating system to each square foot or square meter of the building, and then choose the most appropriate rating system based on the resulting percentages. The entire gross floor area of a LEED project must be certified under a single rating system and is subject to all prerequisites and attempted credits in that rating system, regardless of mixed construction or space usage type. If a rating system is appropriate for less than 40% of the gross floor area of a LEED project building or space, then that rating system should not be used. If a rating system is appropriate for more than 60% of the gross floor area of a LEED project building or space, then that rating system should be used. If an appropriate rating system falls between 40% and 60% of the gross floor area, project teams must independently assess their situation and decide which rating system is most applicable1.

References: LEED v4: Building Design + Construction Guide, LEED Rating System Selection Guidance1

Question #71

A design team is working on a hospital project. In order to meet the Energy and Atmosphere Prerequisite, Minimum

Energy Performance, what option is used?

  • A . Whole building simulation
  • B . EPA target finder rating tool
  • C . Green-e Energy
  • D . Advanced building core performance guide

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

The Whole Building Simulation option is used to meet the Energy and Atmosphere Prerequisite, Minimum Energy Performance for a hospital project. This option involves creating a detailed computer model of the building to simulate its energy performance and identify opportunities for improvement.

References: LEED AP Building Design + Construction (LEED AP BD+C) V4 resources1

Question #72

A new commercial building is being designed to use small capacity air handling units. To meet the requirements of the Carbon Dioxide Monitoring strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Environmental Quality Strategies, where would CO2 monitors need to be located?

  • A . In each occupied space
  • B . In each densely occupied space
  • C . In each occupied space and outdoors
  • D . In each occupied space over 500 ft2 (46 m2)

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

According to the LEED v4 Reference Guide for Building Design and Construction, the Carbon Dioxide Monitoring strategy requires CO2 monitors to be located in each densely occupied space, which is defined as a space with a design occupant density of 25 people or more per 1,000 square feet (93 square meters).This strategy is intended to provide feedback on ventilation system performance and indoor air quality12References:1: LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Enhanced Indoor Air Quality Strategies, Option 2: Additional Enhanced IAQ Strategies, Strategy 3: Carbon Dioxide Monitoring, page 704.2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1019.

Question #73

Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week.

Which of the following actions should be the project team’s top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?

  • A . Take appropriate measures for the safe collection, storage and disposal of batteries
  • B . Make a waste stream projection for the entire year based on the six hours of the waste stream study
  • C . Make a waste stream projection for the entire week, based on the six hours of the waste stream study
  • D . Extend the waste stream study to cover a representative time period of a minimum of 24 hours to identify the top five recyclable waste streams

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4 Reference Guide for Building Design and Construction, the project team must conduct a waste stream audit to identify the top five recyclable waste streams generated by the building and its occupants. The audit must cover a representative time period of a minimum of 24 hours, and must account for variations in the type and quantity of waste generated by different building uses and operations. The project team must then provide dedicated areas for the collection and storage of these materials for recycling. The project team must also provide dedicated areas for the collection and storage of batteries, mercury-containing lamps, and electronic waste, or demonstrate that a local program is in place to properly dispose of these materials.

References:

LEED v4 Reference Guide for Building Design and Construction, Materials and Resources Prerequisite:

Storage and Collection of Recyclables, page 5441

LEED v4 Credit Tutorials: Materials & Resources (BD+C/ID+C), Prerequisite: Storage and Collection of Recyclables2

Question #74

Which of the following is true regarding LEED Pilot Credits?

  • A . Pilot Credits are not specific to the rating systems
  • B . Pilot Credits can be attempted in the design review stage only
  • C . A registered Pilot Credit must be replaced on the LEED project’s scorecard if that pilot credit is removed from the Pilot Credit Library
  • D . Pilot Credit feedback surveys must be completed

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

One of the requirements for attempting a pilot credit is to complete a feedback survey after submitting the project for review. The LEED v4 Reference Guide for Building Design and Construction states that "the project team must complete a feedback survey for each pilot credit attempted. The survey link is provided in the pilot credit language. The survey must be completed after the project has been submitted for review and before the project receives a final rating"1. The feedback survey is an important tool for USGBC to evaluate the effectiveness and applicability of the pilot credit, and to make improvements or modifications based on the project team’s experience.

References:

• LEED v4 Reference Guide for Building Design and Construction, Innovation Credit: Pilot, page 7571

• Pilot credits and pilot alternative compliance paths (ACPs)2

Question #75

LEED project boundaries that include multiple similar buildings which are all eligible for certification can be registered as which of the following?

  • A .   Batch project
  • B . Group project
  • C . Master Site project
  • D . Neighborhood project

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

LEED project boundaries that include multiple similar buildings which are all eligible for certification can be registered as a group project. A group project allows multiple buildings (or interior spaces within multiple buildings) on a shared site to be certified as a single LEED project. These projects must meet the criteria outlined in the LEED Campus Guidance for Projects on a Shared Site, such as having the same construction contract, ownership, management, space type, rating system, and compliance paths. A group project will receive one certification and rating for the entire group.

References: Group Projects (previously Multiple Building Projects), CAGBC News, September 1, 2020.

Question #76

What percentage of a building’s surface area may be excluded from the calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 2. Renovation of Abandoned or Blighted Buildings because of deterioration or damage when maintaining existing building structure, enclosure and interior structural elements?

  • A . 5%
  • B . 10%
  • C . 25%
  • D . 50%

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

For the Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 2. Renovation of Abandoned or Blighted Buildings, up to 25% of the building surface area may be excluded from the credit calculation due to deterioration or damage1.

References:

LEED Certification- Requirements for Material & Resource Credit: Building Life-Cycle Impact Reduction – First green Consulting Pvt Ltd

Question #77

U.S. Green Building Council (USGBC)’s vision for using LEED internationally includes

  • A . allowing more stringent credit requirements for countries outside of the U.S. so that all projects can achieve LEED
  • B . creating multiple LEED rating systems for different countries
  • C . modifying U.S. reference standards, such as ASHRAE 90.1, to be more appropriate for regions outside the U.S.
  • D . providing opportunities for alternative compliance paths that meet the unique needs of a particular region

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

USGBC’s vision for using LEED internationally is to promote green building practices that are globally applicable, locally relevant, and culturally sensitive1. To achieve this vision, USGBC provides opportunities for alternative compliance paths (ACPs) that meet the unique needs of a particular region, such as climate, codes, standards, market conditions, and priorities2. ACPs are modifications or additions to existing LEED credits or prerequisites that recognize regional differences and allow for more flexibility and applicability of LEED3. ACPs are developed by USGBC in collaboration with local green building councils, experts, and stakeholders, and are reviewed and approved by the LEED Steering Committee3. ACPs are available for various regions and countries, such as China, India, Brazil, Europe, and Canada2.

References:

LEED International | U.S. Green Building Council

Alternative Compliance Paths (ACPs) | U.S. Green Building Council

USGBC’s 2020 vision will use LEED to further global connectedness | U.S. Green Building Council

LEED Reference Guide for Building Design and Construction v4

Question #78

Every location in the U.S. identifies how many regional credits?

  • A . Four
  • B . Five
  • C . Six
  • D . Seven

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

Every location in the U.S. identifies four regional credits that are of particular importance for that region. These credits are selected by the USGBC regional councils and chapters based on the environmental, social, and public health issues that are relevant for their areas. A project can earn up to four bonus points by achieving these regional credits.

References:

• LEED v4 BD+C Reference Guide, page 6081

• Regional Priority (RP) credits C U.S. Green Building Council2

Question #79

Which of the following strategies will aid in reducing indoor water use?

  • A . Design drip irrigation for landscape
  • B . Use high-efficiency HVAC systems
  • C . Exclude janitor closets in the building
  • D . Optimize consumption of showerheads

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4: Building Design + Construction Guide, one of the strategies to reduce indoor water use is to optimize the consumption of showerheads by selecting fixtures that have a flow rate lower than the baseline of 2.0 gallons per minute (gpm) at 80 psi, or a local equivalent for projects outside the U.S. This can help the project achieve the Water Efficiency Prerequisite, Indoor Water Use Reduction, and the Water Efficiency Credit, Indoor Water Use Reduction, by reducing the aggregate water consumption from plumbing fixtures and fittings by at least 20% from the baseline1.

The other choices are not strategies to reduce indoor water use, because:

– Designing drip irrigation for landscape is a strategy to reduce outdoor water use, not indoor water use1.

– Using high-efficiency HVAC systems is a strategy to reduce energy use, not water use, although it may have some indirect water savings by reducing the cooling tower water use2.

– Excluding janitor closets in the building is not a feasible or practical strategy, as janitor closets are necessary for cleaning and maintenance purposes, and may also be required by codes or standards3.

References: LEED v4: Building Design + Construction Guide, Water Efficiency Prerequisite, Indoor Water Use Reduction, Requirements1; LEED v4: Building Design + Construction Guide, Water Efficiency Credit, Indoor Water Use Reduction, Requirements1; LEED v4: Building Design + Construction Guide, Energy and Atmosphere Credit, Optimize Energy Performance, Requirements2; LEED v4: Building Design + Construction Guide, Indoor Environmental Quality Credit, Green Cleaning – High-Performance Cleaning Program, Requirements3

Question #80

What are the three phases within the Integrative Process Credit, Integrative Process?

  • A . Pre-design, Discovery, Design and Construction
  • B . Discovery, Design and Construction, Operations and Feedback
  • C . Schematic Design, Design and Construction, Operations and Feedback
  • D . Design Charrette, Schematic Design, Operations and Feedback

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

The Integrative Process credit requires the project teams to perform analyses for both energy- and water-related systems from the predesign phase to the design and construction phase. The project teams should also identify and use opportunities to achieve synergies across disciplines and building systems.

References:

• LEED Integrative Process Credit Explained – Projectific, Inc.

• CI-v4 IPc1: Integrative process | LEEDuser

• The Integrative Process in LEED V4 ― ArchEcology

• New LEED Integrative Process Credit Encourages Design-Build

Question #81

Which of the following is required to earn Energy and Atmosphere Credit, Renewable Energy Production if using a Solar Photovoltaic System?

  • A . Carbon offsets
  • B . Daylighting strategies
  • C . Passive solar strategies
  • D . Produced electricity consumed on-site

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

The Energy and Atmosphere Credit, Renewable Energy Production rewards projects that use renewable energy systems to offset building energy costs1. According to the LEED Reference Guide for Building Design and Construction2, the credit has two options: Option 1. On-Site Renewable Energy and Option 2. Off-Site Renewable Energy. Option 1 requires the project to use renewable energy systems that are located on the project site and that produce electricity or thermal energy for the project. The amount of renewable energy production is calculated based on the percentage of the annual energy cost that is offset by the renewable energy systems. Option 2 requires the project to use renewable energy systems that are located off the project site and that are owned by the project or have a long-term contract with the project. The amount of renewable energy production is calculated based on the percentage of the annual energy use that is offset by the renewable energy systems.

Therefore, among the given options, only Option D is relevant to the credit requirements, as it implies that the solar photovoltaic system is located on the project site and that the produced electricity is consumed by the project. The other options, such as carbon offsets, daylighting strategies, and passive solar strategies, are not directly related to the credit requirements, although they may have other benefits for the project.

References:

Renewable Energy Production | U.S. Green Building Council

LEED Reference Guide for Building Design and Construction v4

Solar Photovoltaic Technology Basics | Department of Energy

Photovoltaic system – Wikipedia

Question #82

Qualifying spaces for the Sustainable Sites Credit. Places of Respite must tgj

  • A . be located outdoors near a water feature
  • B . be located at least 20 ft. (6 m) from a smoking area
  • C . have provisions for direct medical care to be delivered in the area
  • D . have options for shade or indirect sun for a portion of seating spaces

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED AP BD+C V4 reference guide for Healthcare, places of respite must be outdoors or located in interior spaces with views of nature, and have options for shade or indirect sun for a portion of seating spaces. The other options are either incorrect or not required by the credit. References: LEED AP BD+C V4 reference guide for Healthcare, Places of respite

Question #83

Which of the following standards needs to be followed to comply with Indoor Environmental Quality Credit, Thermal Comfort?

  • A . ASHRAE 55-2010
  • B . ASHRAE 62.1-2010
  • C . ASHRAE 90.1-2010
  • D . ASHRAE 189.1-2010

Reveal Solution Hide Solution

Correct Answer: A
A

Explanation:

To comply with Indoor Environmental Quality Credit, Thermal Comfort, the standard that needs to be followed is ASHRAE 55-2010, Thermal Environmental Conditions for Human Occupancy, with errata or a local equivalent1.This standard specifies the combinations of indoor thermal environmental factors and personal factors that will produce thermal environmental conditions acceptable to a majority of the occupants within the space2. The standard also provides methods for measuring and evaluating thermal comfort, as well as guidance for design, operation, and maintenance of thermal comfort systems2.

References: Thermal comfort;ASHRAE 55-2010

Question #84

Which of the following products must always be included in Materials and Resources credits?

  • A . Faucets
  • B . Furniture
  • C . Interior Paint
  • D . Fire suppression system

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Interior paint must always be included in Materials and Resources credits. This is because interior paint is considered as a permanently installed product, which is defined by the LEED v4 Reference Guide for Building Design and Construction as "a product that is installed in a project permanently or semi-permanently, such that removal would require demolition or substantial renovation."1Permanently installed products must be included in the calculations for the following Materials and Resources credits: Building Life-Cycle Impact Reduction, Building Product Disclosure and Optimization – Environmental Product Declarations, Building Product Disclosure and Optimization – Sourcing of Raw Materials, and Building Product Disclosure and Optimization

– Material Ingredients.1The other options are not always included in Materials and Resources credits. Faucets (option A) and fire suppression systems (option D) are considered as mechanical, electrical, and plumbing components, which are excluded from the scope of Materials and Resources credits unless they are specifically addressed by the credit requirements.1Furniture (option B) is considered as a non-permanently installed product, which is optional to include in Materials and Resources credits, except for the Building Product Disclosure and Optimization – Material Ingredients credit, where furniture must be included if it is within the project scope.1References: LEED v4 Reference Guide for Building Design and Construction, p.5791; LEED v4 Reference Guide for Building Design and Construction, p.5801; LEED v4 Reference Guide for Building Design and Construction, p.5811; LEED v4 Reference Guide for Building Design and Construction, p.5821; LEED v4 Reference Guide for Building Design and Construction, p.5831

Question #85

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

  • A . The general contractor
  • B . A LEED AP
  • C . The project’s mechanical engineer
  • D . The owner or an owner’s representative

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

According to the LEED v4: Building Design + Construction Guide, the owner or an owner’s representative must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design. The owner or an owner’s representative is responsible for establishing the project’s vision, goals, budget, and schedule, as well as defining the owner’s project requirements (OPR) and participating in the design charrettes and reviews1. The owner or an owner’s representative also plays a key role in ensuring the continuity and alignment of the project’s performance and environmental objectives throughout all phases of the project1.

The other choices are not mandatory members of the integrated project team, although they may be involved in the integrative process depending on the project’s scope and needs. The general contractor is typically hired after the design phase and may not be involved in the predesign and schematic design analyses required by the prerequisite1.A LEED AP is a professional who has demonstrated knowledge and experience in applying the LEED rating system, but is not required to be part of the integrated project team, although it is recommended and rewarded by the LEED credit, Integrative Process1. The project’s mechanical engineer is one of the possible design consultants who may contribute to the integrative process, especially for the energy-related systems analysis, but is not required to be part of the integrated project team1.

References: LEED v4: Building Design + Construction Guide, Integrative Process Prerequisite, Integrative Project Planning and Design, Requirements1

Question #86

In a large industrial or commercial building, which energy end uses are classified as systems composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering?

  • A . HVAC air system for air conditioning
  • B . Electrical lighting system during peak use hours
  • C . Water flow system used for public faucets and toilets
  • D . Condenser water system with a cooling tower and condenser water pumps

Reveal Solution Hide Solution

Correct Answer: D
D

Explanation:

A condenser water system with a cooling tower and condenser water pumps is classified as a system composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering. This is because the condenser water system is a single energy end use that serves a specific function and can be isolated from other systems1. HVAC air system, electrical lighting system, and water flow system are not considered as single energy end uses, but rather as multiple energy end uses that serve different functions and cannot be easily isolated2.

References:

• LEED v4 for Building Design and Construction, p. 415

• Advanced Energy Metering, p. 2

Question #87

Which of the following is a leadership extraction practice that rewards projects for choosing materials with closed-loop recycling and take-back programs in LEED?

  • A . Material reuse
  • B . Bio-based elements
  • C . Extended producer responsibility
  • D . Forest Stewardship Council (FSC) wood products

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

Extended producer responsibility

Extended producer responsibility is a leadership extraction practice that encourages manufacturers to take back their products or packaging at the end of their useful life and recycle them in a closed-loop system. This reduces the environmental impacts of extraction, transportation, and disposal of raw materials. LEED rewards projects for choosing materials that have extended producer responsibility programs or policies in place.

References:

Reference Guide for Building Design and Construction v4 C Pages 263-2641

LEED v4: Building Design + Construction Guide – U.S.Green Building Council2

Question #88

Which of the following is the location of CO2 sensors in naturally ventilated spaces to comply with the Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

  • A . At least 6 ft. (2 m) above the floor
  • B . At least 3 ft. (1 m) away from windows
  • C . Between 3 ft. and 6 ft. (1 m and 2 m) above the floor
  • D . On the ceiling 3 ft. (1 m) away from adjacent walls

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

According to the LEED v4: Building Design + Construction Guide, the location of CO2 sensors in naturally ventilated spaces to comply with the Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance is between 3 ft. and 6 ft. (1 m and 2 m) above the floor. This is one of the requirements for Option 2. Naturally Ventilated Spaces, which applies to projects that rely on natural ventilation for all or part of the occupied spaces. The CO2 sensors must be located in each zone with natural ventilation openings, and must be capable of generating an alarm when the CO2 concentration exceeds the design value1.

The other choices are not correct, because:

At least 6 ft.(2 m) above the floor is the location of CO2 sensors in mechanically ventilated spaces, not naturally ventilated spaces1.

At least 3 ft.(1 m) away from windows is a general guideline for locating CO2 sensors, but it does not specify the height above the floor2.

On the ceiling 3 ft.(1 m) away from adjacent walls is not a recommended location for CO2 sensors, as it may not reflect the actual CO2 concentration at the breathing zone of the occupants2.

References: LEED v4: Building Design + Construction Guide, Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance, Option 2. Naturally Ventilated Spaces, Requirements1; ASHRAE Standard 62.1-2016, User’s Manual, Chapter 6, Section 6.2.72

Question #89

The Solar Reflectance Index (SRI) includes the measure of a material’s

  • A . color (shade of gray)
  • B . ability to reflect solar radiation
  • C . ability to absorb solar radiation
  • D . ability to reflect thermal radiation

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

The Solar Reflectance Index (SRI) is a measure of the roof’s ability to reject solar heat, as shown by a small temperature rise. It is defined so that a standard black (reflectance 0.05, emittance 0.90) is 0 and a standard white (reflectance 0.80, emittance 0.90) is 100. SRI is calculated using the roof surface’s Solar Reflectance (SR) and Thermal Emittance (TE). SR is the fraction of solar energy that is reflected by the roof, and TE is the relative ability of the roof surface to radiate heat. Therefore, SRI includes the measure of a material’s ability to reflect solar radiation, but not its ability to absorb or emit thermal radiation.

References:

What is the Solar Reflectance Index? – Cool Roof Rating Council

Definitions and Terms | HEATISLAND

Question #90

The contractor has submitted waste hauling reports for review in order to achieve Materials and Resources Credit, Construction and Demolition Waste Management.

Which of the following materials on the documentation contribute towards the credit?

  • A . Excavated soil
  • B . Wood derived fuel
  • C . Items sent to the local incinerator
  • D . Alternate Daily Cover

Reveal Solution Hide Solution

Correct Answer: B
B

Explanation:

This option requires the project to classify wood derived fuel as a recycled material that contributes towards the credit, because it is a waste material that is converted into a useful energy source1. Wood derived fuel can be used for heating, electricity generation, or co-firing with other fuels2. According to the LEED v4: Building Design + Construction Guide, recycled materials are those that have been reprocessed or remanufactured from recovered materials3.

References: = LEED v4: Building Design + Construction Guide, Wood Derived Fuels – an overview | ScienceDirect Topics, Wood-Derived Fuels | Energy and the Environment | US EPA.

Question #91

A LEED Building Design and Construction: Schools project pursuing Location and Transportation Credit, Green Vehicles elects to follow Option 2. Green Buses or School-Owned Vehicles.

What action must the project take to meet the Option 2 requirements?

  • A . Install a preferred drop-off lane for buses meeting the emission requirements
  • B . Provide calculations showing that the average fleet bus meets the emission requirements
  • C . Inventory the school fleet to develop and create a plan for all buses to meet the emission requirements
  • D . Document that all buses serving the project achieve a minimum green score of 30 on the American Council for an Energy Efficient Economy (ACEEE) annual vehicle rating guide

Reveal Solution Hide Solution

Correct Answer: C
C

Explanation:

According to the LEED v4: Building Design + Construction Guide, Option 2 of the Location and Transportation Credit, Green Vehicles requires the project to inventory the school fleet to develop and create a plan for all buses to meet the emission requirements. The plan must include a timeline for implementation and a budget. The emission requirements are based on the U.S. Environmental Protection Agency (EPA) standards for heavy-duty vehicles1. References: LEED v4: Building Design + Construction Guide, Location and Transportation Credit, Green Vehicles, Option 2: Green Buses or School-Owned Vehicles1

Exit mobile version