Upon completion of hardware installation and configuration for a new deployment, the NEXT thing the AV Project Manager should have scheduled is
A . training the client.
B . testing and verification.
C . invoicing and project close out.
D . preventative maintenance schedule.
Answer: B
Explanation:
Upon completion of hardware installation and configuration for a new deployment, the next thing the AV Project Manager should have scheduled is testing and verification. This step ensures that all installed equipment functions correctly and meets the project specifications. It involves checking system performance, resolving any issues, and confirming that the setup works as intended. Axis Technology Specialist documentation underscores the critical role of thorough testing and verification in delivering a successful AV project.