To which of the following objects can you assign external process steps? Note: There are 2 correct answers to this question.

To which of the following objects can you assign external process steps? Note: There are 2 correct answers to this question.
A . Delivery item type
B . Packaging specification
C . Work center
D . Handling unit type

Answer: C, D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments