To determine possible credit compliance for Energy and Atmosphere Credit, Advanced Energy Metering, what information needs to be verified?
To determine possible credit compliance for Energy and Atmosphere Credit, Advanced Energy Metering, what information needs to be verified?
A . That the meter data is remotely accessible
B . That the meter is capable of storing data for at least 12 months
C . That the meter(s) can be manually read
D . That the meter(s) record data at a minimum of 15 minute intervals
Answer: D
Explanation:
The correct answer is D because the meter(s) must record data at a minimum of 15 minute intervals to comply with Energy and Atmosphere Credit, Advanced Energy Metering, as stated in the LEED
v4.1 O+M Reference Guide1. This requirement ensures that the meter data is granular enough to
capture the variations in energy consumption and demand, and to enable the identification of
energy saving opportunities1. The other options are incorrect because they are either not required or
relevant for this credit.
Reference: LEED v4.1 O+M Reference Guide, page 149
Guide to the LEED AP Operations and Maintenance (O+M) Exam, page 91 LEED v4 AP O+M Mock Exam, page 87
Latest LEED AP O+M Dumps Valid Version with 166 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund