The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:
A . Total float
B . Remaining duration
C . Free float
D . Just-in-time scheduling

Answer: A

Explanation:

Total float is the amount of time that an activity can be delayed from its earliest start date without delaying the project completion date or violating a schedule constraint. It is calculated as the difference between the latest allowable end time and the earliest allowable end time of a schedule activity.

For instance, if an activity can be delayed by a certain number of days without affecting the overall project timeline, that delay period represents the total float. This concept is essential in project scheduling because it allows flexibility in managing activities without compromising the project’s final deadline.

Latest CCP Dumps Valid Version with 189 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments