Which item is an example of personnel assessment?

Which item is an example of personnel assessment?A . Resource calendarB . Tight matrixC . Team-building activityD . Focus groupView AnswerAnswer: D

March 8, 2020 No Comments READ MORE +

Which is an enterprise environmental factor?

Which is an enterprise environmental factor?A . Marketplace conditionsB . Policies and proceduresC . Project files from previous projectsD . Lessons learned from previous projectsView AnswerAnswer: A

March 8, 2020 No Comments READ MORE +

In the Plan Stakeholder Management process, expert judgment is used to:

In the Plan Stakeholder Management process, expert judgment is used to:A . Provide information needed to plan appropriate ways to engage project stakeholders.B . Ensure comprehensive identification and listing of new stakeholders.C . Analyze the information needed to develop the project scope statement.D . Decide the level of engagement of...

March 8, 2020 No Comments READ MORE +

The Define Scope process is in which of the following Process Groups?

The Define Scope process is in which of the following Process Groups?A . InitiatingB . PlanningC . Monitoring and ControllingD . ExecutingView AnswerAnswer: B

March 8, 2020 No Comments READ MORE +

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:A . exploitB . avoidC . mitigateD . shareView AnswerAnswer: C

March 7, 2020 No Comments READ MORE +

Which activity is an input to the Conduct Procurements process?

Which activity is an input to the Conduct Procurements process?A . Organizational process assetsB . Resource availabilityC . Perform Integrated Change ControlD . Team performance assessmentView AnswerAnswer: A

March 7, 2020 No Comments READ MORE +

The zero duration of milestones in project planning occurs because milestones:

The zero duration of milestones in project planning occurs because milestones:A . Are unpredictable and challenge the Plan Schedule Management process.B . Occur at random times in the project plans.C . Represent a moment in time such as a significant project point or event.D . Represent both significant and insignificant...

March 7, 2020 No Comments READ MORE +

What do the Google Drive and Box integrations require to properly function with Alfresco Process Services?

What do the Google Drive and Box integrations require to properly function with Alfresco Process Services?A . There needs to be a valid development account to access the APC . There needs to be a SHA2 security token.D . There needs to be a secret key.E . There needs to...

March 7, 2020 No Comments READ MORE +

An output of the Manage Stakeholder Engagement process is:

An output of the Manage Stakeholder Engagement process is:A . change requestsB . enterprise environmental factorsC . the stakeholder management planD . the change logView AnswerAnswer: A

March 7, 2020 No Comments READ MORE +

An input to Develop Project Charter is a/an:

An input to Develop Project Charter is a/an:A . Business case.B . Activity list.C . Project management plan.D . Cost forecast.View AnswerAnswer: A

March 7, 2020 No Comments READ MORE +