A recently promoted project manager must facilitate the weekly status update meeting, what should the project manager do to ensure a productive meeting?

A recently promoted project manager must facilitate the weekly status update meeting, what should the project manager do to ensure a productive meeting?A . Avoid or smooth over any disagreements.B . Carefully read the latest meeting minutes.C . Limit attendance to the project team and stakeholders.D . Circulate a defined...

January 2, 2021 No Comments READ MORE +

What should the project manager do?

A vendor communicates that the delivery of a project item will be delayed by two weeks. What should the project manager do?A . Conduct a variance analysis.B . Implement the Perform Integrated Change Control processC . Review the contract clause for liquidated damagesD . Identify a way to conduct schedule...

January 2, 2021 No Comments READ MORE +

A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?

A project's original budget at completion (BAC) was calculated as US$100,000, but the estimate at completion (EAC) is US$120,000 if the schedule performance index (SPI) is equal to 1, what is the cost performance index (CPI)?A . Equal to 1.2B . Less than 1C . Equal to 1D . Greater...

January 2, 2021 No Comments READ MORE +

What should the project manager do?

A project manager discovers an enhancement that will improve the design being developed by a subject matter expert (EME). What should the project manager do?A . Disregard the enhancement, as no changes are allowed.B . Ask the expert to implement the enhancement.C . Ask the change control board (CCB) to...

January 2, 2021 No Comments READ MORE +

What should the project manager do?

Prior to the implementation of a system upgrade, a team member discovers a critical detect in the current system mat must be fixed. What should the project manager do?A . Take no further actions since the project scope has been finalized.B . Implement the fix and install it with the...

January 1, 2021 No Comments READ MORE +

What should the project manager recommend to the project sponsor?

A project to replace a core business system is required by a company's CEO. The CEO appoints a project sponsor, and urges an immediate start to the project. The project sponsor asks the project manager―who has no previous experience with such a complex project―to write the project charter. What should...

January 1, 2021 No Comments READ MORE +

What should the project manager have done to avoid this?

A design team discovers that the work breakdown structure (WBS) created by the project manager is missing key tasks. What should the project manager have done to avoid this?A . Reviewed historical information from previous projectsB . Developed an Ishikawa diagramC . Created a requirements traceability matrixD . Sought expert...

January 1, 2021 No Comments READ MORE +

What should the project manager do to close the project?

Work on a project passes the customer acceptance test and the customer expresses appreciation. What should the project manager do to close the project?A . Notify the steering committee.B . Obtain a letter of recommendation from the customerC . Obtain formal acceptance from the customerD . Notify the project sponsor...

January 1, 2021 No Comments READ MORE +

What should the project manager do next?

After preparing the work breakdown structure (WBS), the project manager is ready to assign task areas to project team members. Subsequently, the project sponsor asks to add requirements that the team feels are unachievable. What should the project manager do next?A . Evaluate the impact of the request on the...

January 1, 2021 No Comments READ MORE +

What should the project manager do to mitigate this risk using the risk transference strategy?

During risk analysis for a building renovation project, it is discovered that the building contains toxic materials that must be removed. What should the project manager do to mitigate this risk using the risk transference strategy?A . Ask the client to remove the toxic materials and exclude this work from...

January 1, 2021 No Comments READ MORE +