What document is produced from this activity?
A matrixed organization has a history of project schedule and cost overruns. A new project manager learns of this history and wants to avoid the trend. The project manager works with the project team to define, validate, and control all required work to complete the project successfully What document is...
What would be the critical path(s)?
A project has live finish-to-start (FS) activities - Activity A takes one day. - Activity B follows A and takes five days - Activity C follows B and takes two days. - Activity D follows B and A and takes two days. - Activity E is preceded by C and...
Which document confirms whether the vendor should do this testing?
The project manager discovers that the vendor did not perform software technical testing. Which document confirms whether the vendor should do this testing?A . Procurement management planB . Statement of work (SOW)C . Scope management plan D Product scope descriptionView AnswerAnswer: B
What should the project team do to benefit from this phase?
Phase two of a complex, multi-phase project is completed, and the customer accepts the deliverables. What should the project team do to benefit from this phase?A . Measure customer satisfaction.B . Document and share lessons learnedC . Obtain additional resourcesD . Perform a risk analysis.View AnswerAnswer: B
What should the project manager do first?
All quality controls have passed, and a project deliverable is ready to be released to the customer However, a change request to add new quality criteria has been approved. What should the project manager do first?A . Update the project management planB . Stop the release of the deliverable to...
What should the project manager do?
A company has a history of implementing system integration projects using their-in-house software with a vendor infrastructure A project manager, new to the company, has no prior experience with vendor integration projects What should the project manager do?A . Refer to the project statement of work (SOW)B . Review the...
What document should the project manager use to ensure that payment delay information is documented for this project?
A company has a longstanding client who is often late with payment. The company now has a new project with this client. What document should the project manager use to ensure that payment delay information is documented for this project?A . Risk management planB . Historical information and lessons learned...
What final action should the project manager take before moving to the new project?
A project manager delivered the final project report and is ready to close the project. The company is anxious to start an important project and asks the project manager to start the new assignment immediately What final action should the project manager take before moving to the new project?A ....
What should the project manager have done to avoid this?
A project sponsor informs a project manager that even though a completed project was on schedule, within budget, and met scope requirements, the customer is dissatisfied with the final product. What should the project manager have done to avoid this?A . Scheduled more meetings while developing the quality management plan.B...
What should the project manager do?
A project manager implements an information system for a financial company. A senior It manager indicates that quality control has not identified any failures and that the new system is ready for end users What should the project manager do?A . Transfer the product lo the clientB . Distribute the...