What estimating technique should the contractors use?
After approval of a project scope statement, requests for proposal (RFP) are sent to potential contractors. The project manager indicates that detailed quotes will be required. What estimating technique should the contractors use?A . Top-downB . Bottom-upC . AnalogousD . ParametricView AnswerAnswer: B
Where should the testing requirements have been recorded?
A project manager expected a vendor to complete testing of each component they produced and was surprised to discover that no testing was done. To recover, the project team performs a statistical sampling of the components Where should the testing requirements have been recorded?A . Quality management planB . Procurement...
Where should this information be captured?
During a project steering committee meeting, the project manager reports that a formerly supportive key ream member has become resistant to and negative about changes. Where should this information be captured?A . Responsible, accountable, consult, and inform (RACI) matrixB . Stakeholders engagement assessment matrixC . Risk register and issue logD...
What should the project manager have done to avoid this?
A manufacturing plant project is ready for hand-over to the maintenance manager. The maintenance manager advises that the new plant is noncompliant with the company's maintenance standards. What should the project manager have done to avoid this?A . Updated the communications management planB . Used expert judgmentC . Conducted a...
What is the output of this process?
After a functional team delivers a product the project manager uses statistical sampling and inspection to determine if the product performs as expected What is the output of this process?A . Quality metricsB . Verified deliverablesC . Quality audit reportD . Project scope statementView AnswerAnswer: A
To what should the project manager refer to implement this suggestion?
A team member suggests using a mobile instant messaging application to allow the team to promptly approve measures for improving the project's schedule and costs. To what should the project manager refer to implement this suggestion?A . Stakeholder engagement planB . Schedule baselineC . Change management planD . Scope management...
Which at the following strategies should be used in the project's planning process?
The communication technology being applied in a project was tested in simulated environments but never in actual projects. This lack experience with the technology must be addressed in detail. Which at the following strategies should be used in the project's planning process?A . Provide a status update to senior managementB...
In what plan should these new rules be documented?
A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that new government-imposed rules for the procurement of these materials caused this delay. In what plan should these new rules be documented?A . Project managementB . Communications managementC...
What amount should the contractor be paid?
The project manager of a pipeline project hires a construction contractor using a cost plus fixed fee (CPFF) contract, the contractor provides the project manager with an estimate of US$50,000, and a fixed-fee amount of US$5,000. When the pipeline is completed, the construction cost is US$60,000. What amount should the...
To support the work, what should the project manager do next?
An IT department's deliverable is two weeks late If the deliverable is not completed by the end of the week the project will be placed on hold Within the last two weeks the project manager communicated the issue to the IT department, spoke with the IT project manager and elevated...