What should the project manager do first?
In a multi-site development project, sharing documents within the project team is identified as a security risk Introducing a new software release would mitigate this risk. What should the project manager do first?A . Assess the impact on the projectB . Update the project management plan.C . Review the assumptions...
What should the project manager do to address this?
A project manager is developing a schedule for a communications project. The available project information is vague. What should the project manager do to address this?A . Assign a contingency reserve for uncertain activities.B . Increase the total float of all activities.C . Determine activity durations using three-point estimatingD ....
What skills should the project manager use?
A project manager in a weak-matrix environment must coordinate across the organization. During the execution phase, the project manager needs critical information to address important issues to help the team remove obstacles What skills should the project manager use?A . Conflict managementB . LeadershipC . InfluencingD . Decision-makingView AnswerAnswer: C
What should the project manager do next?
During planning, a project learn documented the possibility that new hardware could arrive up to 45 days late and delay the project's delivery date One month into the project the manufacturer notifies the project manager that the hardware will be shipped 20 days sooner than anticipated What should the project...
In what area should the project manager implement corrective actions?
A project status report shows that the earned value (EV) is 24.5. the schedule performance index (SPI) is 0.92, and the cost performance index (CPI) is 1.08. In what area should the project manager implement corrective actions?A . Project scheduleB . Stakeholder engagementC . Resource managementD . Project costView AnswerAnswer:...
What should the project manager do?
A resource's functional manager requests confidential information about a delayed project Because the functional manager does not have the appropriate authorization level the resource asks permission from the project manager to share the information What should the project manager do?A . Meet with the resource and the functional manager to...
What tool or technique should be used to determine whether or not the variances are within acceptable limits?
A project manager must track schedule variances over time. What tool or technique should be used to determine whether or not the variances are within acceptable limits?A . Scatter diagramB . Cause-and-effect diagramC . Control chartD . Control panel diagramView AnswerAnswer: C
What plan should be reviewed to eliminate these differences?
An organization has contracts with an external supplier to support a critical part of a project Senior management and the project ream have differences about what deliverables the external supplier should provide. What plan should be reviewed to eliminate these differences?A . Delivery management planB . Scope management planC ....
Which process governs the project manager's implementation of the approved change?
A project sponsor decides to add a feature to the project that affects the project cost, schedule, and scope. The change is approved by the change control board. Which process governs the project manager's implementation of the approved change?A . Monitor RisksB . Control Cost and ScheduleC . Direct and...
What document should the project manager review?
An organization initiates a large project in a developing country. The project manager, who is also the local stakeholder is very supportive of this project During project execution the project manager is transferred to another country. The new project manager is less supportive of the project because it uses many...