How should the project manager proceed?
An agile project team is building a new product. The stakeholders require ongoing illustration of project business value. How should the project manager proceed?A . Prepare performance value reports for the business on an ongoing basis.B . Include demonstrations of the built portion of the product at the end of...
What should the project manager do first?
A company has decided to implement a new archiving system A data breach occurred during the implementation of the project What should the project manager do first?A . Implement the planned risk response to handle the issue.B . Review possible alternative documentation methods with teamC . Update the risk register...
What should the project manager do to increase the project's chances of success?
A research and development department is planning to develop a product that will introduce a new line of business for the organization. What should the project manager do to increase the project's chances of success?A . Plan a working session focusing on the scope, vision, and mission of the initiativeB...
What should the project manager do next?
for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier. To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications. What should...
What should the project manager do?
A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other. What should the project manager do?A . Review lessons learned from previous projects that used the same teamB . Review the organizational culture,...
What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?
During a retrospective meeting a project manager hears that stakeholders have been constantly complaining at iteration demos about product features not being delivered as requested. What advice should the project manager give to the Product owner to ensure that product features are always delivered as requested?A . Include stakeholders during...
How should the project manager handle this situation?
After a project learn has been working on a project for several months, the project Is cancelled. The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has...
What should the project manager do in this situation?
A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts. What should the project manager do in this situation?A . Work to understand the key stakeholder's concerns and provide feedback in regular project status reportsB . Arrange an...
What should the project manager do?
The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies What should the project manager do?A . Make sure the project team...
What should the project manager do to ensure timely delivery?
The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates. What should the project...