How should the project manager proceed to schedule the kick-off meeting?
At the end of planning a new project, the project manager needs to schedule the kick-off meeting but is having difficulty finding a common time slot when all necessary stakeholders can be available onsite . How should the project manager proceed to schedule the kick-off meeting?A . Email all stakeholders...
How should the project manager address this situation?
The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements How should the project manager address this situation?A . Ask the team to include the compliance requirement...
What factor should the project manager consider when determining if the project is suitable for an agile approach?
An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach. What factor should the project manager consider when determining if the project is suitable for an agile approach?A . The project is an information...
How can the project manager ensure knowledge transfer across the team?
A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer. The SMEs captured various process deviations without sharing with the project team How can the project manager ensure knowledge transfer across the team?A . Ask the project...
What should the project manager do to handle this situation?
While developing a new product, a key stakeholder expresses concern about insufficient information on product feature requirements. The product team disagrees and mentions that detailed requirements have been provided. What should the project manager do to handle this situation?A . Organize a discussion with the product team to clarify the...
What can the project manager do?
A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference . What can the project manager do? to improve interactions between the team members in both countries?A . Ensure full participation of both the product owner...
How should the customer’s request be managed?
An agile project has just started, and the backlog is being prioritized. The customer wants to prioritize business value over identified risks. How should the customer’s request be managed?A . Accept risks as they decrease over a period of time.B . Create a risk value profile to track the relative...
What artifact should the project manager share with the stakeholder?
The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue . What artifact should the project manager share with the stakeholder?A . Issue logB . Project management planC . Risk management planD...
What strategy should the project manager use in order to keep delivering value in a restricted environment?
The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources What strategy should the project manager use in order to keep delivering value in a restricted environment?A . Reduce the...
What should the project manager do to expedite the project delivery?
A project to implement a new process is still in development. When implemented, the company will benefit by a reduction in utility costs. The project financial evaluation indicates a payback of 3 years. What should the project manager do to expedite the project delivery?A . Increase resources on the technical...