What strategy should the project manager use in order to keep delivering value in a restricted environment?
The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources What strategy should the project manager use in order to keep delivering value in a restricted environment?A . Reduce the...
What should the project manager do?
The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies What should the project manager do?A . Make sure the project team...
What should the project manager do next?
A vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget What...
Which two items should be taken into account first to review and update the product backlog priorities during the meeting?
A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were...
How should the project manager prepare for the next steps of the project?
A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program. How should the project manager prepare for the next...
What should the project manager do?
A project just kicked off and management’s expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?A . Increase the details of the work breakdown structure (WBS) to minimize errors and delays.B...
What should the project manager do first?
A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework. The business wants to keep track of the value delivered by...
What approach should the project manager use?
A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the...
What should the project manager pay special attention to in order to achieve this goal?
During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value. What should the project manager pay special attention to in order to achieve this goal?A . Reviewing and updating the...
How can the project manager promote empowerment and accountability among the team?
A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered. How can the project manager promote empowerment and accountability among the team?A . Assign the tasks individually based on the role...