What type of work order is this?

The NetEco management system supports dispatching corresponding work orders for a certain alarm to track the entire processing process. What type of work order is this? (A . Asset Work Order B. Change Work Order C. Alert Ticket D. Business TicketsView AnswerAnswer: C

September 17, 2022 No Comments READ MORE +

In FusionModule2000, how to adapt the skylight when the column occupies the closed passage space in the scene around the column?

In FusionModule2000, how to adapt the skylight when the column occupies the closed passage space in the scene around the column?A . Customized tempered glass flip skylight B. Field machining with control skylight C. On-site cutting with plexiglass adjustable skylight D. Sealed with special adjustable sealing plate for skylightView AnswerAnswer:...

September 17, 2022 No Comments READ MORE +

The type of circuit breaker used in the sub-circuit of the PDU8000 precision power distribution cabinet. ( )

The type of circuit breaker used in the sub-circuit of the PDU8000 precision power distribution cabinet. ( )A . Disconnect switch B. Molded Case Circuit Breakers C. Miniature circuit breakers D. Frame circuit breakerView AnswerAnswer: C

September 16, 2022 No Comments READ MORE +

Fusionmodule2000 IT cabinet seismic rating? ( )

Fusionmodule2000 IT cabinet seismic rating? ( )A . 7 B. 8 C. 9View AnswerAnswer: C

September 15, 2022 No Comments READ MORE +

Which of the following statements is false about surveillance cameras?

Which of the following statements is false about surveillance cameras?A . Less than 4 cameras can be connected to the ETH socket B. The camera power supply mode is PoE power supply C. The camera can be directly connected to the switch powered by PoE D. Camera data can be...

September 14, 2022 No Comments READ MORE +

The maximum charging capacity of UPS5000-E is ( )

The maximum charging capacity of UPS5000-E is ( )A . 40% B. 20% C. 10% D. 30%View AnswerAnswer: A

September 14, 2022 No Comments READ MORE +

"Data Center Design Specifications" GB50174-2017 stipulates that when selecting a site, a cooling data center should have sufficient water sources.

"Data Center Design Specifications" GB50174-2017 stipulates that when selecting a site, a cooling data center should have sufficient water sources.A . Direct ventilation cooling method B. Indirect fresh air cooling method C. Water evaporative cooling method D. Chilled water cooling methodView AnswerAnswer: C

September 14, 2022 No Comments READ MORE +

it is necessary to pay the RM bill and report the third-party equipment access fee?

The NetEco6000 management system supports access to third-party equipment to achieve centralized management of the computer room; then, when monitoring which of the following equipment is connected to third-party equipment, it is necessary to pay the RM bill and report the third-party equipment access fee? (A . Huawei UPS 5000E...

September 14, 2022 No Comments READ MORE +

Is the channel type of the typical configuration of FusionModule800 a cold aisle or a hot aisle? ( )

Is the channel type of the typical configuration of FusionModule800 a cold aisle or a hot aisle? ( )A . Hot and cold aisle B. Hot AisleView AnswerAnswer: A

September 14, 2022 No Comments READ MORE +

What is the maximum IT load supported by the FusionModule2000 integrated UPS? ( )

What is the maximum IT load supported by the FusionModule2000 integrated UPS? ( )A . 125KW B. 150KW C. 75KW D. 50KWView AnswerAnswer: A

September 13, 2022 No Comments READ MORE +