Which of the following testing metrics would BEST be applied towards testing a distributed audio system for proper speaker wattages and cabling?

Which of the following testing metrics would BEST be applied towards testing a distributed audio system for proper speaker wattages and cabling?A . Low-end system response 60 Hz and belowB . High-end frequency response 10 kHz and aboveC . Audio uniformity in the range of intelligible speech 100 Hz -...

March 15, 2025 No Comments READ MORE +

Which of the following will be VITAL for ensuring that the company meets the deadlines?

A client has ordered a large project from a company. This project has several critical components and a fixed schedule. Which of the following will be VITAL for ensuring that the company meets the deadlines?A . proper job costingB . confirming lead timesC . qualifying the customerD . confirming price...

March 13, 2025 No Comments READ MORE +

What is the name for a written, non-technical narrative that explains system functionality?

What is the name for a written, non-technical narrative that explains system functionality?A . needs analysisB . program reportC . service manualD . performance verificationView AnswerAnswer: B Explanation: A program report is a written, non-technical narrative that explains system functionality. It outlines the operational aspects of the system in a...

March 13, 2025 No Comments READ MORE +

When discussing a proposed audiovisual project with a new customer, it is important for the salesperson to FIRST

When discussing a proposed audiovisual project with a new customer, it is important for the salesperson to FIRSTA . conduct a survey of end users to determine the project goals.B . prepare a detailed layout of the equipment and cabling requirements.C . identify the key decision makers and stakeholders in...

March 10, 2025 No Comments READ MORE +

Network Quality of Service (QoS) is defined as

Network Quality of Service (QoS) is defined asA . the ability to prioritize the traffic in the network system.B . the ability to set the quantity of stations connected via the network.C . the ability to remotely manage network switches, routers and hubs via the network connection.D . a feature...

March 4, 2025 No Comments READ MORE +

When gathering information, it is important to ask about the customer's goals because the

When gathering information, it is important to ask about the customer's goals because theA . customer may have unrealistic expectations of what can be done.B . customer may be planning on moving before the project is complete.C . integrator needs to confirm they understand the relationship between desires and budgetD...

February 28, 2025 No Comments READ MORE +

What does the technician need to consider?

An event planner for a banquet surrounding a swimming pool has requested that the pool be lit in the client’s colors using underwater lighting. What does the technician need to consider?A . the IP rating of the fixturesB . access to a grounded power supplyC . whether the installing technicians...

February 26, 2025 No Comments READ MORE +

Before confirming an anticipated completion date with the customer, it is MOST important to

Before confirming an anticipated completion date with the customer, it is MOST important toA . double check the floor finishes.B . ensure the date is not a holiday.C . ensure no components are backordered.D . create the system maintenance schedule.View AnswerAnswer: C Explanation: Before confirming an anticipated completion date, it...

February 25, 2025 No Comments READ MORE +

When calibrating a loudspeaker system, which weight setting on the SPi. meter is used for its mdus>on of low frequency sound levels in the measurement?

When calibrating a loudspeaker system, which weight setting on the SPi. meter is used for its mdus>on of low frequency sound levels in the measurement? A . WeightedB . WeightedC . WeightedD . WeightedView AnswerAnswer: C Explanation: When calibrating a loudspeaker system, the C-weighted setting on an SPL (Sound Pressure...

February 25, 2025 No Comments READ MORE +

What project document(s) would determine responsibility?

On a construction project awarded through a competitive process, the electrical contractor says that the AV company is responsible for the installation of conduit. What project document(s) would determine responsibility?A . estimateB . submittalsC . proposal cover letterD . bid (tender) documentsView AnswerAnswer: D Explanation: The responsibility for the installation...

February 24, 2025 No Comments READ MORE +