Which of the following factors is important in a software product m terms of its adaptability?

Which of the following factors is important in a software product m terms of its adaptability?A . EfficiencyB . AccessibilityC . TrainabilityD . PortabilityView AnswerAnswer: D Explanation: Portability refers to the ease with which software can be transferred from one environment to another. It is a critical factor in a...

August 23, 2024 No Comments READ MORE +

Which of the following steps comes first during release planning for waterfall-type projects?

Which of the following steps comes first during release planning for waterfall-type projects?A . Define the scope of the software being developed.B . Determine which problems will be corrected in the next release.C . Select the set of requirements that will be included in the release.D . Confirm the implemented...

August 23, 2024 No Comments READ MORE +

In which of the following ways do metadata requirements guarantee everyone is interpreting data consistently?

In which of the following ways do metadata requirements guarantee everyone is interpreting data consistently?A . It ensures that everyone who has access to the data has a consistent under standing of its meaning and use.B . It ensures that data is managed, maintained, and used appropriately through its lifecycle...

August 22, 2024 No Comments READ MORE +

At what point in the development lifecycle should change control be implemented?

At what point in the development lifecycle should change control be implemented?A . During the requirements phaseB . During the implementation phaseC . At the beginning of the design phaseD . When the testing phase beginsView AnswerAnswer: A Explanation: Change control should be implemented during the requirements phase of the...

August 22, 2024 No Comments READ MORE +

Which of the roles in an organizational change management core team see the need for change and will help sell it to the organization?

Which of the roles in an organizational change management core team see the need for change and will help sell it to the organization?A . Change sponsorsB . Change advocatesC . Official change agentsD . Informal change agentsView AnswerAnswer: A Explanation: Change sponsors are typically high-level leaders within an organization...

August 22, 2024 No Comments READ MORE +

Which of the following baselines is typically established after completion and approval of system requirements?

Which of the following baselines is typically established after completion and approval of system requirements?A . ProductB . AllocatedC . FunctionalD . DevelopmentView AnswerAnswer: C Explanation: The functional baseline is typically established after the completion and approval of system requirements. This baseline includes the functional requirements and specifications that describe...

August 21, 2024 No Comments READ MORE +

When a software change order is reviewed by the change control board (CCB), it is assigned a status from which of the following sets of classifications?

When a software change order is reviewed by the change control board (CCB), it is assigned a status from which of the following sets of classifications?A . Accepted, evaluated, m progressB . Approved, disapproved, deferredC . Escalated, rejected, in progressD . Escalated, proposed, acceptedView AnswerAnswer: B Explanation: When a software...

August 21, 2024 No Comments READ MORE +

During what time period is the software configuration management plan implemented?

During what time period is the software configuration management plan implemented?A . From the requirements phase through the maintenance phase of the software lifecycleB . After the software product is placed into productionC . From the requirements phase through the testing phase of the software lifecycleD . During the code...

August 21, 2024 No Comments READ MORE +

Which of the following software metrics is based on a nominal scale-1

Which of the following software metrics is based on a nominal scale-1A . Root cause of defect, logic error data definition, etcB . Severing of a defect, critical, major, minor, etc.C . Defect density: number per function point, etc.D . Defect discovery rate: number detected per day, etc.View AnswerAnswer: A...

August 20, 2024 No Comments READ MORE +

Which of the following tests should be conducted on software that will be used internationally?

Which of the following tests should be conducted on software that will be used internationally?A . Logical path analysisB . Predefined function keysC . Boundary value analysisD . Test matricesView AnswerAnswer: D Explanation: Test matrices are essential for software that will be used internationally because they help organize and manage...

August 19, 2024 No Comments READ MORE +