Which task settings should be configured to meet these requirements?
The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed. Which task settings should be configured to meet these requirements?A . The task Duration should be set to 2 days. A predecessor with a Finish-Start...
Which action should the stakeholder take to log the risk?
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk. Which action should the stakeholder take to log the risk?A . Log a risk as part of...
Why may this be the case?
Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday. Why may this be the case?A . The primary task owner has time off logged in Workfront.B...
What is the appropriate action for the project manager to take?
A project manager is assigned to a new Workfront request. The request specifies that the management team’s sign-off is needed before the project can begin. What is the appropriate action for the project manager to take?A . Convert the issue into a project using a project template.B . Email the...
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?A . Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.B . Visit the Reports...
When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?
When a project owner grants Contribute access on a project to a user with the same access level as the project owner, what can that user do?A . Add a custom formB . Attach a template to the projectC . Add tasksView AnswerAnswer: A Explanation: In Workfront, users with "Contribute"...
An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes. In which project area does this information reside?
An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes. In which project area does this information reside?A . Queue DetailsB . Project DetailsC . MetricsView AnswerAnswer: B. Explanation: Adobe Workfront, information about the Group and Portfolio assigned to a project is...
Which field should the manager reference to view all task assignees?
A project manager wants to see all of the assignees for each task in a project. Which field should the manager reference to view all task assignees?A . Assigned ToB . AssignmentsC . AssignedView AnswerAnswer: B Explanation: In Adobe Workfront, the "Assignments" field allows a project manager to see all...
What impact does this have on the project progress status?
A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it. What impact does this have on the project progress status?A . The next...
Which report grants the executive team this visibility?
The executive team at Company A has asked the Workfront System Administrator how they can get visibility into the health, importance, and strategic alignment of active projects across the organization so that they can quickly make data-driven business decisions. Which report grants the executive team this visibility?A . A project...