Six Sigma refers to a process whose output has 100% of its data points within 8 Standard Deviations from the Mean.
- A . True
- B . False
Training cost $2,500 and a project required an initial investment of $23,500. If the project yields monthly savings of $2,500 beginning after 4 months, what is the payback period in months (before money costs and taxes)?
- A . 7.2
- B . 10.4
- C . 14.4
- D . 28.8
The ROI for a project is a measurement metric that stands for _____________________ and is one of the methods used to measure the success of a Lean Six Sigma project.
- A . Return on Investment
- B . Recognition of Innovation
- C . Recovery of Investment
- D . Return on Inventory
The DMAIC approach to problem solving stands for Define, __________, Analyze, Improve and Control.
- A . Manage
- B . Measure
- C . Memorize
- D . Manipulate
Voice of the Business is a Lean Six Sigma technique to determine the needs and wants of the ______________ of the business.
- A . Owners
- B . Managers
- C . Debt holders
- D . Staff
Y, the output of a process, is the ______________ variable while Xn, the various inputs to a process, are the _____________ variables.
- A . Independent, dependent
- B . Individual, multiple
- C . Sole, multiple
- D . Dependent, independent
Which of the following would likely be a CTQ (Critical-to-Quality) for the purchase of a service?
- A . Documentation is clear
- B . Was timely in delivery
- C . Required no redo
- D . All of these answers are correct
Al bought a digital camera from his local electronics store. When he first used it he found the zoom lens function was inoperative because a gear was installed improperly.
For the manufacturer of the camera this would be categorized as what type of cost?
- A . Internal Failure Cost
- B . Prevention Cost
- C . External Failure Cost
- D . Appraisal Cost
The formula Y = f(Xn) is a method of expressing the concept that the output of a process is a function of all the __________________?
- A . Materials and labor
- B . Inputs to the process
- C . Line personnel and direct supervision
- D . Employees of the company
A Belt has determined that the insurance claim form needn’t be reviewed by accounting thereby improving the number of claims a processer can handle. According to Cost of Poor Quality (COPQ) definitions RTY improvement would be considered _______________.
- A . Downsizing savings
- B . Median savings
- C . Soft savings
- D . Hard savings