Question #1

How long at a maximum is Iteration Planning?

  • A . 2 hours
  • B . 6 hours
  • C . 1 day
  • D . 4 hours

Reveal Solution Hide Solution

Correct Answer: D
Question #2

Exploration Enabler stories

  • A . Build the Architectural Runway, which enables smoother and faster development
  • B . Facilitate specific activities such as verification and validation, documentation, signoffs, regulatory submissions, and approvals
  • C . Build understanding of what is needed by the Customer to understand prospective Solutions and evaluate alternatives
  • D . Build development and testing frameworks that enable a faster and more efficient development process

Reveal Solution Hide Solution

Correct Answer: C
Question #3

It is recommended to select no more than 2 improvement items as outcome of the Iteration retrospective

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: B
Question #4

Which of the following artifacts can be used to gain understanding of the lead time?

  • A . burnup chart
  • B . pareto chart
  • C . fishbone diagram
  • D . cumulative flow diagram

Reveal Solution Hide Solution

Correct Answer: D
Question #5

Program Agility is one of the Core Competencies of Business Agility.

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: B
Question #6

Pl System Demo is often led by

  • A . Product Management
  • B . All of the above
  • C . POs
  • D . System Team

Reveal Solution Hide Solution

Correct Answer: B
Question #7

Which of the below are Core Competencies for Business Agility?

  • A . Team and Technical Agility
  • B . Lean-Agile Leadership
  • C . Organizational Agility
  • D . Continuous Learning Culture

Reveal Solution Hide Solution

Correct Answer: A, B, C, D
Question #8

Which of the following are used to track status?

  • A . burnup chart
  • B . pareto chart
  • C . fishbone diagram
  • D . cumulative flow diagram

Reveal Solution Hide Solution

Correct Answer: A, D
Question #9

To grow a self-organizing team, leaders must provide

  • A . hierarchy
  • B . rule book
  • C . trust
  • D . autonomy

Reveal Solution Hide Solution

Correct Answer: C, D
Question #10

The whole team needs to be involved in co-creation of the Definition of Done.

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: B
B

1 1. Who manages the Program backlog in SAFe?


Question #11

By organizing the second operating system around_________ instead of ________, SAFe offers a way for enterprises to focus on customers, products, innovation, and growth

  • A . departments, value streams
  • B . products, features
  • C . features,components
  • D . value streams, departments

Reveal Solution Hide Solution

Correct Answer: D
Question #12

The Test Pyramid advocates a balanced portfolio of tests with many small, low-level, manual tests and fewer large, automated tests .

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: A
Question #13

SAFe advocates to develop on demand and release on cadence.

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: A
Question #14

Velocity is

  • A . measurement for economic benefit
  • B . business value delivered (monetary)
  • C . average hours of work done by the team
  • D . the rate (in story points) at which the team delivers

Reveal Solution Hide Solution

Correct Answer: D
Question #15

What is the typical cadence for PI Planning?

  • A . 6 to 8 weeks
  • B . 2-4 weeks
  • C . 8-12 weeks
  • D . 3 to 5 weeks

Reveal Solution Hide Solution

Correct Answer: C
Question #16

By their very nature, value streams are short-lived and generally dependent on each other

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: B
Question #17

How long is the Iteration Review?

  • A . 6 hours
  • B . 1 day
  • C . 1 to 2 hours
  • D . 4 hours

Reveal Solution Hide Solution

Correct Answer: C
Question #18

Who establishes the sequence of backlog items based on program priorities, events, and dependencies with other teams?

  • A . Business Owner
  • B . Scrum Master
  • C . Product Owner
  • D . RTE

Reveal Solution Hide Solution

Correct Answer: C
Question #19

Who acts as the Customer for Developer requests?

  • A . Scrum Master
  • B . Product Owner
  • C . Business Owner
  • D . Epic Owner

Reveal Solution Hide Solution

Correct Answer: B
B

2 1. How many members does SAFe recommend to be in one Agile team?


Question #20

How many are the Scrum events?

  • A . three
  • B . depends on the length of the iteration
  • C . four
  • D . seven

Reveal Solution Hide Solution

Correct Answer: C

Question #21

Which component of the Continuous Delivery Pipeline is the ability to make value available to customers all at once, or in a staggered fashion based market and business needs?

  • A . Release On Demand
  • B . Continuous Exploration
  • C . Continuous Integration
  • D . Continuous Deployment

Reveal Solution Hide Solution

Correct Answer: A
Question #22

Which of the following is the recommended approach to create T-shaped skills on the ART?

  • A . rotating team members between different teams
  • B . Cross-training
  • C . Pair-programming
  • D . All of the above

Reveal Solution Hide Solution

Correct Answer: D
Question #23

Scrum and Kanban cannot be used together C either of the two needs to be chosen to be implemented.

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: B
Question #24

Which the simplest SAFe configuration?

  • A . Program
  • B . Large Solution
  • C . Portfolio
  • D . Essential

Reveal Solution Hide Solution

Correct Answer: D
Question #25

How many pillars does the House of Lean have?

  • A . five
  • B . four
  • C . seven
  • D . three

Reveal Solution Hide Solution

Correct Answer: B
Question #26

How many are the Agile Manifesto values?

  • A . four
  • B . seven
  • C . five
  • D . twelve

Reveal Solution Hide Solution

Correct Answer: A
Question #27

What does the R in the SMART model for PI Objectives stand for?

  • A . Reliable
  • B . Rare
  • C . Relatable
  • D . Realistic

Reveal Solution Hide Solution

Correct Answer: D
Question #28

Which 2 of the below are true for NFRs (non-functional requirements)?

  • A . They are split into Features and acceptance criteria is established
  • B . They are part of an Epic Hypothesis Statement
  • C . They stay in the Portfolio Backlog until implementation capacity is available
  • D . They are associated with backlogs at all four levels of SAFe
  • E . They provide visibility to large business initiatives

Reveal Solution Hide Solution

Correct Answer: B, D
B, D

3 1. What does INVEST stand for in the context of good user stories?


Question #29

Which of the below are dimensions of the Team and Technical Agility competency?

  • A . Built-in Quality
  • B . Team of Agile Teams
  • C . Agile Teams
  • D . Technical Excellence

Reveal Solution Hide Solution

Correct Answer: A, B, C
Question #30

If there is no historical data of team velocity, how many story points are allocated for every full-time developer and tester on the team?

  • A . 5
  • B . 13
  • C . 8
  • D . 23

Reveal Solution Hide Solution

Correct Answer: C

Question #31

Which of the following are Scrum events?

  • A . Iteration Inspection
  • B . Iteration Review
  • C . Iteration Planning
  • D . Iteration Status Session

Reveal Solution Hide Solution

Correct Answer: B, C
Question #32

The continuous delivery pipeline is part of which business agility competency?

  • A . Continuous Integration
  • B . Agile Product Delivery
  • C . Continuous Learning Culture
  • D . Lean Portfolio Management

Reveal Solution Hide Solution

Correct Answer: B
Question #33

The Agile Manifesto consists of 4 values and how many principles?

  • A . seven
  • B . twelve
  • C . five
  • D . ten

Reveal Solution Hide Solution

Correct Answer: B
Question #34

Which of the following is not a primary responsibility of Product Management?

  • A . Developing the Vision and Roadmap for the ART
  • B . Facilitating PI Planning
  • C . Owning and managing the Program Backlog
  • D . Understanding the customer needs

Reveal Solution Hide Solution

Correct Answer: B
Question #35

SAFe Lean-Agile principles support centralised decision-making.

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: A
Question #36

What is ART sync event at program level?

  • A . There is no such event in SAFe
  • B . Sync of all people on the ART
  • C . Combined PO Sync and Scrum of Scrums
  • D . Sync between the ScrumMasters and the Business Owners

Reveal Solution Hide Solution

Correct Answer: C
Question #37

Which of the following are acceptable measures expressed by the M in the SMART model for PI Objectives?

  • A . a range
  • B . quantitative measures
  • C . descriptive measures
  • D . All of the above

Reveal Solution Hide Solution

Correct Answer: D
D

4 1. Which of the below are not part of the CALMR approach to DevOps?


Question #38

When is the Acceptance Criteria for Features typically defined?

  • A . during Program Backlog refinement
  • B . during Iteration Planning
  • C . during PI Planning
  • D . during Inspect & Adapt

Reveal Solution Hide Solution

Correct Answer: A
Question #39

Code review or Pair Programming is a practice recommended in?

  • A . Kanban
  • B . Scrum
  • C . Waterfall
  • D . XP

Reveal Solution Hide Solution

Correct Answer: D
Question #40

Which of the following is true for the Backlog Refinement Session?

  • A . Most of the focus is on the next Iteration, but it allows time to discuss future Iterations and even Features for the next Pl
  • B . Provides enough time to identify and resolve dependencies and issues that could impact the next Iteration
  • C . Helps the team think about new Stories prior to Iteration Planning
  • D . All of the above

Reveal Solution Hide Solution

Correct Answer: D

Question #41

Kanban teams establish and publish Iteration goals, which consist of the known parts of their work

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: A
Question #42

What does the I in the INVEST mnemonic for good user stories stand for?

  • A . Independent
  • B . Implementable
  • C . Interesting
  • D . Immutable

Reveal Solution Hide Solution

Correct Answer: A
Question #43

Which team level event follows the 12th principle of the Agile Manifesto?

  • A . Iteration Review
  • B . Daily Standup
  • C . Iteration Retrospective
  • D . Iteration Planning

Reveal Solution Hide Solution

Correct Answer: C
Question #44

What does the Continuous Delivery Pipeline enable?

  • A . Release on Demand
  • B . Quarterly Release
  • C . Annual Release
  • D . Scheduled Releases

Reveal Solution Hide Solution

Correct Answer: A
Question #45

Who fosters team adoption of Agile technical practices?

  • A . ystem Architect
  • B . Lead developer
  • C . Scrum Master
  • D . Technical Lead

Reveal Solution Hide Solution

Correct Answer: C
Question #46

A self-organizing team does not interact with the organization.

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: A
A

5 1. Which of the below are not part of the CALMR approach to DevOps?


Question #47

During Iteration Planning, the Scrum Master presents the stories in order of priority and answers clarifying questions

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: B
Question #48

Who accepts the User Stories?

  • A . Agile Team
  • B . Product Owner
  • C . Senior Management
  • D . Scrum Master

Reveal Solution Hide Solution

Correct Answer: B
Question #49

Uncommitted objectives don’t count in velocity/capacity.

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: A
Question #50

Which of the following is not a type of Enabler story?

  • A . Infrastructure
  • B . Testing
  • C . Compliance
  • D . Exploration

Reveal Solution Hide Solution

Correct Answer: B

Question #51

Architectural Runway must be continuously maintained

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: A
Question #52

What is the primary goal of assigning business value to PI Objectives?

  • A . to help the teams on the train prioritize work
  • B . to show economic impact to the customer
  • C . none of the above
  • D . to have Business Owner buy-in

Reveal Solution Hide Solution

Correct Answer: A
Question #53

Business Agility is the ability to compete and thrive in the digital age by quickly responding to market changes and emerging opportunities with innovative, digitally-enabled business solutions

  • A . TRUE
  • B . FALSE

Reveal Solution Hide Solution

Correct Answer: A
Question #54

A research story, considered an exploration style Enabler is called

  • A . spike
  • B . slice
  • C . smell
  • D . stretch task

Reveal Solution Hide Solution

Correct Answer: A
Question #55

Agile Product Delivery is one of the Core Competencies of Business Agility.

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: B
B

6 1. Which one of the below is not one of the Core Competencies for Business Agility?


Question #56

The team has to find a balance between commitment and adaptability. Too little commitment can lead to what negative consequences?

  • A . lower cost
  • B . better quality
  • C . unpredictability
  • D . lack of focus on results

Reveal Solution Hide Solution

Correct Answer: C, D
Question #57

Features are split into User Stories and Enabler Stories which are then implemented during the iterations of the PI

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: B
Question #58

PI objectives do not need to be written down and verbal expression is enough

  • A . FALSE
  • B . TRUE

Reveal Solution Hide Solution

Correct Answer: A
Question #59

Which of the following is not a Scrum event?

  • A . Iteration Review
  • B . Iteration Planning
  • C . Iteration Retrospective
  • D . Weekly Report Out

Reveal Solution Hide Solution

Correct Answer: D
Exit mobile version