Question #1

When would MoV NOT be of use?

  • A . When determining the value of a decommissioned asset
  • B . During the transition of an asset into the operational environment
  • C . When an asset is in the operational environment
  • D . During the delivery stage of a project

Reveal Solution Hide Solution

Correct Answer: A
Question #2

In which situation should caution be used in deciding whether to apply MoV?

  • A . IT projects
  • B . Products and services with a high value score
  • C . Policy-making
  • D . Lobbying for support

Reveal Solution Hide Solution

Correct Answer: B
Question #3

Which is a correct distinction between Value Engineering and Value Analysis?

  • A . Value Engineering is applied to improve evolving designs and Value Analysis is applied to improve existing products
  • B . Value Engineering is applied to manufactured and constructed products and Value Analysis is applied to services and business processes
  • C . Value Analysis is applied to determine required cost and performance targets and Value Engineering is applied to realize those targets
  • D . Value Analysis and Value Engineering, while similar, differ in that they employ different process steps

Reveal Solution Hide Solution

Correct Answer: A
Question #4

Which is a key component of the Frame the Programme or Project process?

  • A . Initial briefing meeting
  • B . Team selection
  • C . Resource analysis
  • D . Idea selection

Reveal Solution Hide Solution

Correct Answer: A
Question #5

Which statement regarding the steps in the Generic MoV Study Plan is true?

  • A . The final step should be to develop the Value Improving Proposals
  • B . The first step should be to define the MoV Study objectives
  • C . The Implementation Plan should be agreed before setting targets for benefits improvement
  • D . The Value Drivers should be prioritized before identifying the functions

Reveal Solution Hide Solution

Correct Answer: B
Question #6

How many phases does the MoV Value Engineering Job Plan contain?

  • A . Six
  • B . Ten
  • C . Twelve
  • D . Eight

Reveal Solution Hide Solution

Correct Answer: D
Question #7

Which would NOT be used to estimate the operating and running costs for a new IT system?

  • A . The operating costs of a similar IT implementation
  • B . The current daily rate of specialist skills required to operate the system
  • C . An estimate of how many staff would be required to run the new system
  • D . The total expenditure on MoV Studies

Reveal Solution Hide Solution

Correct Answer: D
Question #8

Which is NOT required for a top-down approach to introducing MoV to an organization?

  • A . Providing guidance on how MoV will be used on projects
  • B . Setting up a strategy for implementing MoV Policy
  • C . Establishing an internal resource skilled in the application of MoV
  • D . Developing procedures for data capture and feedback

Reveal Solution Hide Solution

Correct Answer: C
Question #9

Which is a main method of Function Analysis?

  • A . Value Improving Proposal
  • B . Value Tree
  • C . Discounted Cash Flow
  • D . Brainstorming

Reveal Solution Hide Solution

Correct Answer: B
Question #10

Which is an MoV Principle?

  • A . Understand and articulate value
  • B . Process information
  • C . Focus on functions and required outcomes
  • D . Prioritize value

Reveal Solution Hide Solution

Correct Answer: C

Question #11

Which is NOT a recommended action in constructing an Option Evaluation Matrix?

  • A . Select criteria
  • B . Define scale of improvement required and sensitivity ranges
  • C . Set targets
  • D . Establish weights for relative importance

Reveal Solution Hide Solution

Correct Answer: C
Question #12

Which statement regarding prioritizing value is true?

  • A . A project can be successful even if it delivers only the Value Drivers classed as critical
  • B . Prioritizing value should be based only on financial Value Drivers
  • C . Value Drivers will normally be allocated different levels of importance
  • D . Prioritizing value should be carried out with members of the project team rather than the project’s end users

Reveal Solution Hide Solution

Correct Answer: C
Question #13

When should an organization consider it necessary to establish in-house MoV delivery capability?

  • A . When MoV is running only on a project-by-project basis
  • B . When the scale of MoV applications becomes large and frequent enough to justify an internal delivery capability
  • C . When a third party procurement is running successfully
  • D . When it can benefit from more effective use of internal resources by broadening their capabilities

Reveal Solution Hide Solution

Correct Answer: B
Question #14

On a FAST diagram, where would you expect to find functions with the lowest level of abstraction?

  • A . On the far right of the diagram
  • B . On the far left of the diagram
  • C . At the bottom of the diagram
  • D . Anywhere – there is no relationship between level of abstraction and location on the diagram

Reveal Solution Hide Solution

Correct Answer: A
Question #15

Which statement regarding the Function Analysis Systems Technique is true?

  • A . Functions should describe the features of a product rather than what it does
  • B . A Primary Basic Function consists of one or more Higher Order Functions
  • C . A Primary Basic Function consists of one or more Primary Supporting Functions
  • D . Moving from the Higher Order Function to the Primary Basic Function answers the question "How do we do this?"

Reveal Solution Hide Solution

Correct Answer: D
Question #16

Which technique focuses on underlying issues, rather than solving specific problems?

  • A . Root Cause Analysis
  • B . Soft Systems Methodology
  • C . Value Profiling
  • D . Cost Function Analysis

Reveal Solution Hide Solution

Correct Answer: A
Question #17

Which method provides a good checklist for communication during an MoV study?

  • A . Brainstorming
  • B . Five Ws and an H
  • C . Function Analysis
  • D . Cost/Worth

Reveal Solution Hide Solution

Correct Answer: B
Question #18

Which is a reason why MoV should be applied throughout the Investment Decision?

  • A . To minimize the number of points where decisions need to be made
  • B . To ensure that information used to make a decision is used only in that decision
  • C . To maximize value in the face of evolving requirements
  • D . To ensure that reviews such as those conducted under the Gateway Review Process will be positive

Reveal Solution Hide Solution

Correct Answer: C
Question #19

What is the worth of a Function?

  • A . Its relative importance
  • B . The current cost of performing it
  • C . The lowest cost at which it could be performed
  • D . Its objective

Reveal Solution Hide Solution

Correct Answer: C
Question #20

Which statement about MoV is true?

  • A . It supports decision-making based on minimizing value for money
  • B . It encourages innovation outside of an organization’s goals
  • C . It facilitates optimal balance between investment and long-term operating expenditure
  • D . It removes resources from consideration when reviewing organizational needs

Reveal Solution Hide Solution

Correct Answer: C

Question #21

What is the purpose of Function Analysis?

  • A . To analyze what things do
  • B . To analyze what things are
  • C . To define how to produce things
  • D . To define how much things cost to produce

Reveal Solution Hide Solution

Correct Answer: A
Question #22

Who prepares each Value Improving Proposal?

  • A . The MoV Study Leader
  • B . The Programme Owner, who assesses relevant value priorities during Value Profiling
  • C . The Value Metric Owner
  • D . The owner of the relevant idea or scenario allocated during the selection process

Reveal Solution Hide Solution

Correct Answer: D
Question #23

Which is NOT an area where it is necessary to strike a balance in order to maximize value?

  • A . Reconciling the needs and views of different stakeholders
  • B . Balancing capital and operating costs
  • C . Balancing the use of resources to reflect their availability and the organization’s priorities
  • D . Balancing the overall benefits realized against the use of resources

Reveal Solution Hide Solution

Correct Answer: B
Question #24

Which statement regarding the MoV processes is true?

  • A . All processes will be used at all stages in a project lifecycle
  • B . MoV activities change as a project evolves from inception to use
  • C . They are only applicable to project environments
  • D . They are most applicable at the inception stage of a project

Reveal Solution Hide Solution

Correct Answer: B
Question #25

Which is NOT a key element of stakeholder consultation?

  • A . Ensuring that all major stakeholders for the project have been identified and engaged
  • B . Ensuring that the same stakeholder representatives are involved throughout the project
  • C . Ensuring that stakeholders are provided with timely, specific and clear information regarding proposals and their impacts throughout the development process
  • D . Ensuring that regular feedback on progress is given

Reveal Solution Hide Solution

Correct Answer: B
Question #26

Which will be included in the MoV Project Plan?

  • A . Identification of suitable candidates to lead and participate in the Studies
  • B . Key attributes of a proposed Study
  • C . Constraints applicable to a proposed Study
  • D . A draft function diagram

Reveal Solution Hide Solution

Correct Answer: A
Question #27

What are the key activities involved in the Processing Information stage?

  • A . Preparation, facilitation, creativity and innovation
  • B . Analysis, creativity and innovation, and evaluation and selection
  • C . Preparation, target-setting, facilitation, and creativity and innovation
  • D . Selection of team, preparation of Study Handbook, analysis of data, creativity and Innovation

Reveal Solution Hide Solution

Correct Answer: A
Question #28

What is provided by a Value Improving Proposal (VIP)?

  • A . Information which the decision-makers need in order to decide whether to implement the VIP in full, partially, or not at all
  • B . A detailed record of the existing situation that the VIP is intended to improve, including the functions carried out
  • C . Information which Senior Management needs in order to implement the VIP
  • D . A detailed implementation plan for each VIP

Reveal Solution Hide Solution

Correct Answer: A
Question #29

Which is a purpose of the MoV Project Plan?

  • A . To provide a means of prioritizing stakeholders
  • B . To provide information to aid decision-makers when deciding whether to authorize a project
  • C . To describe the purpose of a series of MoV Studies throughout a project
  • D . To test early models or prototypes before a design is fixed

Reveal Solution Hide Solution

Correct Answer: C
Question #30

Which MoV document contains a detailed evaluation of options for value improvement?

  • A . MoV Project Plan
  • B . Value Improving Proposal
  • C . MoV Study Handbook
  • D . MoV Progress Report

Reveal Solution Hide Solution

Correct Answer: B