What is the first step the project manager should take to gather customer requirements?
A new project manager is planning an information security project for a company that resides in different countries. What is the first step the project manager should take to gather customer requirements?A . Conduct a stakeholder analysis to identify how regional policies may influence needsB . Request relevant stakeholders to...
What should the project manager do to address this issue?
A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated. What should the project manager do to address this issue?A . Create a...
What should the project manager do?
A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date What should the project manager do?A . Hold a stakeholder meeting to align timelines and scope expectations.B . Crash the schedule to shorten the...
How should the project manager address this concern moving forward?
Having managed a similar project while working with previous stakeholders, a project team decided to use the same report format they used in the earlier project. However, stakeholders new to the project are not fully comprehending the status of the project based on the reports that are being circulated. How...
What should the project manager do?
A project manager is managing an innovation project for a big corporation. The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email What should the project manager do?A . Contact the sponsor to...
What artifact should the project manager share with the stakeholder?
The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?A . Issue logB . Project management planC . Risk management planD ....
Which statement is true?
A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50. The actual expenditure is US$2,000 and 50 user stories have been delivered. Which statement is true?A . The project is on budget and...
How should the project manager effectively approach this situation?
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system. How should the project...
The team has reported the following impediments at the daily standup meeting
DRAG DROP The team has reported the following impediments at the daily standup meeting. Drag each impediment on the left to the action that the project manager needs to take on the right View AnswerAnswer:
What should the project lead do next?
A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again What should the project lead do next?A . Notify...