What should the project manager do?
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected. What should the project manager do?A . Submit a change request to the change control board (CCB) in...
What should the project manager have done to avoid this?
A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project...
What should the project manager do?
A project manager is managing an innovation project for a big corporation. The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email. What should the project manager do?A . Contact the sponsor to...
Which three key factors does the project manager need in order to deliver this product?
A company's leadership team has decided to invest in a new product using an agile approach. The commercial and product teams have started the planning activity for this new venture. Which three key factors does the project manager need in order to deliver this product? (Choose 3)A . High-level product...
What should the project manager have done to prevent this situation from occurring?
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective. What should the project manager have done to prevent this situation from occurring?A . Analyzed the sponsor's...
What should the project manager do?
A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs. What should...
What approach should the project manager take?
A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data Some external stakeholders are reluctant to provide support. What approach should the project manager take?A . Examine the...
What action should the project manager take to motivate the project team's performance?
A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage. The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s...
What should the project manager do first?
A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management. What should the project manager do first?A . Review the benefits of the proposed changes in relation to the business case. beB . Assess...
What should the project manager do?
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams. The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly. What should the project manager do?A . Arrange a...