What should the project manager do?
During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned . What should the project manager do?A . Check with the team to learn what can be done,...
What should the project manager do?
An international client contacted a software development company to build out a software product, and an agile project manager was assigned. At one of the review meetings, the client complains that a feature mentioned at the initial debriefing was not implemented. What should the project manager do?A . Include the...
What should the project manager do?
A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and...
What should the project manager do?
During the executing phase, a project manager is reviewing the issue log and finds there are outstanding high-priority issues that are still open. Most of the open issues require effort from external domain experts who are not on the project team. What should the project manager do?A . Ask the...
What should the project manager do first?
During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?A . Ask upper management for more...
What should the project manager do first?
After a project has been approved, a key stakeholder tells the project manager that the current project management strategy is not well defined. The project manager is also informed that the key stakeholder does not want to hold a working session What should the project manager do first?A . Share...
What should the project manager do?
A project manager is working with an agile team. A key stakeholder who does not join the sprint planning session is very unhappy, as the delivery date for the final product has been pushed back three times . What should the project manager do?A . Meet with the stakeholder to...
What should the project lead do next?
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months. What should the project lead do next?A ....
Who is responsible for analyzing the new requirement and making the final decision?
On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner's requirements. Who is responsible...
Match the scenario on the left with the action on the right
DRAG DROP During a project's planning session, the project team discussed selecting the required information to be included in the monthly progress report This report will be produced in the Executing and Monitor and Controlling phases and will be used when communicating project progress to the client Match the scenario...