What should the project manager do?
An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team What should the project manager do?A . The project manager should...
What factor should the project manager consider when determining if the project is suitable for an agile approach?
An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach. What factor should the project manager consider when determining if the project is suitable for an agile approach?A . The project is an information...
What should the project manager do first?
During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?A . Ask upper management for more...
How should the project manager have handled documentation for the project?
During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated. How should the project manager have handled documentation for the project?A . Updated the project management...
On what should the project manager focus?
A marketing team is developing ideas in order to revamp an existing product. The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch. On what should the project manager focus?A . Ensuring that the team is also focused...
What is one of the key activities that the project manager should undertake to ensure company success?
A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings. What is one of the key activities that the project manager should undertake to ensure company success?A . Review the project...
How should the project manager handle this situation?
A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors. The project is ongoing and uses a hybrid approach. The project will be conducted in multiple sites, with several development...
What can the project manager do to help increase the team's motivation and engagement with the project?
A project team has recently finished a sprint for developing two features for a fleet management system Although the team delivered the required features, they encountered several issues and conflicts during the sprint. Team members were upset about this experience and are now showing a lack of motivation due to...
How should the project manager handle this moving forward?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of...
Which of the following statements is correct?
400pm (rate-per-minute) -> reduces the power and brakes the engine Which of the following statements is correct?A . 0 1,600 rpm is a project risk, 1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.B . 1,600 rpm is a project issue, 1,500...