What does CPI value less than 1.0 indicates?
- A . Cost overrun for work completed
- B . Scheduled performance is great
- C . Cost underrun of performance to date
- D . Cost for completed work is as per estimate
You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart.
What is this phenomenon called?
- A . Rule of Improvement
- B . Mean Improvement
- C . Rule of Seven
- D . Low-Riding Mean
A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building.
Which of the following correctly defines the organization in program management terminology?
- A . Negative stakeholder
- B . Positive stakeholder
- C . Key stakeholder
- D . Hurdle stakeholder
You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to.
All of the following are themes that you can discuss with Marcy except for which one is not a program theme?
- A . Stakeholder management
- B . Requirements analysis
- C . Benefits management
- D . Program governance
You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years . The program is currently 30 percent complete and you have spent $789,000 . The program is supposed to be 35 percent complete but do to some delays you’re slightly behind
schedule. Based on this information, what is the schedule performance index (SPI) for this program?
- A . $821,065
- B . .86
- C . 1.05
- D . .89
You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them.
Which of the following processes are you on?
- A . Report Program Performance
- B . Monitor and Control Program Scope
- C . Monitor and Control Program Schedule
- D . Monitor and Control Program Performance
The program manager has a global program with five component projects . The program sponsor wants the management plans, processes/procedures, and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?
- A . Accept what the program sponsor requires and implement the changes.
- B . Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor the best option.
- C . Respond to the program sponsor if the program sponsor asks about it a second time.
- D . Present the risks and benefits of the changes to the program sponsor.
Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB.
What document should you provide to Hal?
- A . Invoice
- B . Proposal
- C . Bid
- D . Quote
A small, regional utility closes a customer rewards program and transitions it to operations . The executive sponsor and program manager are concerned about the impact on benefits realization. The program manager assures the executive sponsor that any corrective actions will be included in the next phase.
What should the program manager do to ensure a successful transition?
- A . Ask each project manager to consolidate and file all program documentation in the corporate archives.
- B . Obtain all project manager’s contact information, and then have them reassigned back to their functional managers.
- C . Ask the program’s business analyst to collect all project information and create a report.
- D . Ensure that all program documents, including lessons learned, are archived in the knowledge repository.
Which earned value management formula can help you determine how likely it is that you’ll complete the program based on the amount of cash left in the program budget?
- A . Estimate at completion
- B . Variance at completion
- C . To-complete performance index
- D . Estimate to complete