Question #1

The primary purpose of creating a minimally viable product (MVP) is to:

  • A . Commit to continuous improvement by adding value
  • B . Establish the validity of a hypothesis by putting a prototype in front of customers
  • C . Finalize the product design through a series of experiments
  • D . Create a marketable product complete with useful features

Reveal Solution Hide Solution

Correct Answer: B
Question #2

Which artifact collects all the work flowing to the team?

  • A . Business backlog
  • B . Iteration backlog
  • C . Product backlog
  • D . Release roadmap

Reveal Solution Hide Solution

Correct Answer: B
Question #3

DevOps refers to:

  • A . Automating the testing effort in the team
  • B . Creating a smooth flow of work from development to operations
  • C . Involving operational teams in the development work
  • D . Using development team members to solve operational problems

Reveal Solution Hide Solution

Correct Answer: B
Question #4

Usually the first step in deciding the team’s way of working is to:

  • A . Connect the dots
  • B . Analyze the context
  • C . Make some initial choices
  • D . Coach setting the stage

Reveal Solution Hide Solution

Correct Answer: B
Question #5

True or False: Fulfilling the requirements means that we delighted our customer

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #6

Which of the following is NOT a desirable practice in design thinking?

  • A . Be conscious about the constraints in the solution space
  • B . Being empathetic to the customers
  • C . Look for solutions appropriate for the situation
  • D . Make design choices early in the project

Reveal Solution Hide Solution

Correct Answer: D
Question #7

Which of the following is one of the process goals in the transition stage?

  • A . Produce a potentially consumable solution
  • B . Develop common vision
  • C . Ensure production readiness
  • D . Address risk

Reveal Solution Hide Solution

Correct Answer: C
Question #8

A team lead works very hard to get the team to collaborate and gel together as a unit. The team lead believes that teamwork will ultimately result in the best results for the business.

Which principle was applied?

  • A . Be awesome
  • B . Choice is good
  • C . Context counts
  • D . Optimize around products/services
  • E . Delight customers

Reveal Solution Hide Solution

Correct Answer: A
Question #9

The principle "Organize around products/services" means that:

  • A . Customers should be asked to pick from the available products or services
  • B . Building dedicated cross-functional teams focused on customer offerings
  • C . Project teams are best equipped to deliver products

Reveal Solution Hide Solution

Correct Answer: B
Question #10

What is Disciplined Agile (DA) best described as?

  • A . A process-decision toolkit
  • B . An Agile/Lean methodology
  • C . A process-decision framework
  • D . An Agile methodology

Reveal Solution Hide Solution

Correct Answer: A

Question #11

Which is a supporting role a Disciplined Agile (DA) team?

  • A . Stakeholder
  • B . Team Lead
  • C . Specialist
  • D . Architecture Owner

Reveal Solution Hide Solution

Correct Answer: C
Question #12

True or False: Disciplined agile projects try to maximize the work-in-progress so that it can get more work done

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #13

Why is the coordination meeting important for a project team?

  • A . It provides a demo of the product to keep everyone up to date.
  • B . It allows the stakeholders to see how well the team is working together.
  • C . It allows the team to reassess the backlog to meet their needs.
  • D . It provides an opportunity for the team to help itself stay in sync.

Reveal Solution Hide Solution

Correct Answer: D
Question #14

True or False: The FLOW view for Disciplined Agile means that there are no starts and stops in any DA project

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #15

An organization uses a lean startup model to quickly validate ideas and narrow down on candidate projects to pursue.

Which of the DA life-cycles would be most suitable for this setup?

  • A . Continuous delivery Agile
  • B . Agile
  • C . Exploratory
  • D . Lean
  • E . Continuous Delivery Lean
  • F . Program

Reveal Solution Hide Solution

Correct Answer: C
Question #16

Which of the following is NOT a tactical scaling factor for a team?

  • A . Team size
  • B . Geographic distribution
  • C . Team maturity
  • D . Organization distribution

Reveal Solution Hide Solution

Correct Answer: C
Question #17

What is the role of the product owner?

  • A . Coordinate the product
  • B . Organize the product team
  • C . Inspect the product
  • D . Build the right product

Reveal Solution Hide Solution

Correct Answer: D
Question #18

True or False: All the process goal diagrams need to be explored while determining the initial way of working.

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #19

The concept of Lean was developed around eliminating the three types of deviations that shows inefficient allocation of?

  • A . Resources
  • B . Meetings
  • C . Deadlines
  • D . Data

Reveal Solution Hide Solution

Correct Answer: A
Question #20

All of the following are key principles to keep in mind as the team chooses and evolves it’s

Way of Working (WoW) except:

  • A . Pragmatism
  • B . Delight customers
  • C . Choice is good
  • D . Context counts

Reveal Solution Hide Solution

Correct Answer: B

Question #21

What are two of the ways that Disciplined Agile provides a solid foundation for business agility?

  • A . Enforces adherence to organizational standards.
  • B . Provides guidance to streamline processes in a context-sensitive manner.
  • C . Creates awesome teams that foster joy.
  • D . Describes the trade-offs associated with a range of options.
  • E . Defines a framework for agility at scale.

Reveal Solution Hide Solution

Correct Answer: A,B
Question #22

One of the differences between a MVP and a MBI is that:

  • A . MVP is a collection of MBI’s
  • B . MBI is the initial release that is sent to the customer
  • C . MVP represents a product that is released to the customer
  • D . MBI is typically built incrementally on top of an existing product

Reveal Solution Hide Solution

Correct Answer: D
Question #23

Which role on the delivery team builds the product right.

  • A . Team Member
  • B . Team Lead
  • C . Product Owner
  • D . Architecture Owner

Reveal Solution Hide Solution

Correct Answer: D
Question #24

The following process goal usually requires a lot of tailoring:

  • A . Form team
  • B . Prove architecture early
  • C . Accelerate value delivery
  • D . Improve quality

Reveal Solution Hide Solution

Correct Answer: C
Question #25

One of the important changes in the Finance processes in Agile teams is that:

  • A . You will have less oversight over spending as teams are self-organized
  • B . Teams will have a definite budget allocated and will manage to it
  • C . The organization has to be structured around functions like Sales, Development, etc.
  • D . You will not need to monitor cash flows to large extent

Reveal Solution Hide Solution

Correct Answer: C
Question #26

True or False: Enterprise awareness means trying to standardize the processes across all similar teams in the organization.

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #27

Which artifact collects all the work flowing to the team?

  • A . Product backlog
  • B . Business backlog
  • C . Iteration backlog
  • D . Release roadmap

Reveal Solution Hide Solution

Correct Answer: A
Question #28

A team is trying to explore the purpose, the domain and the usage of a product.

Which process goal is being worked on?

  • A . Address changing stakeholder needs
  • B . Align with enterprise direction
  • C . Explore scope
  • D . Identify architecture strategy

Reveal Solution Hide Solution

Correct Answer: C
Question #29

Which of the following life-cycle models is based on continuous flow of work?

  • A . Continuous Delivery Agile
  • B . Program
  • C . Agile
  • D . Lean
  • E . Waterfall
  • F . Exploratory

Reveal Solution Hide Solution

Correct Answer: D
Question #30

For an Agile or Lean project team, which best describes the aim of the Transition phase?

  • A . The team tests the solution and trains end users in the new features of their consumable solution
  • B . The team communicates the coming release to their stakeholders
  • C . The team applies continuous deployment (practices and tools to automate deployment)
  • D . The team ensures that a solution is ready to be released to their stakeholders and then releases it appropriately

Reveal Solution Hide Solution

Correct Answer: D

Question #31

Push is when work is:

  • A . Delayed until later.
  • B . Given to people.
  • C . Expedited to meet a deadline.
  • D . Outsourced to a vendor.

Reveal Solution Hide Solution

Correct Answer: B
Question #32

Your team wants to work in an Agile manner and has been asked to provide a cost estimate for the project even though management recognizes that the requirements will evolve overtime.

Which process goal is most likely to offer potential techniques to address this?

  • A . Project Management
  • B . Plan the Release
  • C . Explore Scope
  • D . Address Changing Stakeholder Needs

Reveal Solution Hide Solution

Correct Answer: C
Question #33

Your team is working on the new release of an existing solution and has discovered that it needs to pay down some existing technical debt.

Which process goal is most likely to offer potential techniques to address this?

  • A . Evolve Way of Working (WoW)
  • B . Address Risk
  • C . Improve Quality
  • D . Secure Funding

Reveal Solution Hide Solution

Correct Answer: C
Question #34

What may NOT be decided during the INCEPTION stage of a Disciplined Agile project?

  • A . Test strategy
  • B . Deployment strategy
  • C . Initial architecture
  • D . High level scope

Reveal Solution Hide Solution

Correct Answer: B
Question #35

Which of the following is false about the Business Operations process blade?

  • A . It requires close collaboration with the Sales and Marketing process blades
  • B . It involves strategies for providing services to the business
  • C . The implementation of this blade will be standard across domains
  • D . It should focus on delighting the customers

Reveal Solution Hide Solution

Correct Answer: C
Question #36

True or False: In general, it is preferable to have long standing product teams rather than ad-hoc or project based teams.

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: A
Question #37

What is the role of the product owner?

  • A . Build the right product
  • B . Organize the product team
  • C . Inspect the product
  • D . Coordinate the product

Reveal Solution Hide Solution

Correct Answer: D
Question #38

True or False: Disciplined Agile roles cover all the possible roles in an organization

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #39

Which of the following is not one of the responsibilities of the architecture owner?

  • A . Work with the product owner to define the technical roadmap
  • B . Mentoring and coaching the team on technical practices
  • C . Work to improve the supportability of the product
  • D . Evaluate the team member’s performance and administer rewards
  • E . Evolving the design and architecture for the product

Reveal Solution Hide Solution

Correct Answer: D
Question #40

The primary function of the "Business Operations" process blade is:

  • A . To provide services to customers and support your products
  • B . To monitor the competitive landscape and come up with appropriate promotional strategies
  • C . To monitor and guide teams to remove any barriers that they may experience
  • D . To ensure cash flow in the organization ensuring that the money is spent well

Reveal Solution Hide Solution

Correct Answer: A

Question #41

What goal diagrams should a team select first?

  • A . The goals in which the team has the least experience.
  • B . The goals that are selected by the customer and stakeholders.
  • C . The goals that are the easiest to complete.
  • D . Goals that are most relevant to the team’s context and life cycle.

Reveal Solution Hide Solution

Correct Answer: D
Question #42

True or False: It is OK if the team’s WoW is initially determined more by the enterprise guidelines or the recommendations of a coach.

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: A
Question #43

Which of the following is a disadvantage of having a feature team as opposed to component teams?

  • A . One team delivers a feature from top to bottom
  • B . There are lesser hand-offs across teams
  • C . Require cross-functional team members
  • D . There is a temptation to build everything from scratch

Reveal Solution Hide Solution

Correct Answer: D
Question #44

A team working on a product grew from 8 to 12 team members. The Scrum master felt that they need to split into two scrum teams. After discussion, they decided to stick to one team as it was better for team cohesiveness and delivery.

This is an example of:

  • A . Enterprise awareness
  • B . Being pragmatic
  • C . Optimize for flow
  • D . Being Awesome
  • E . Choice is good

Reveal Solution Hide Solution

Correct Answer: B
Question #45

Your organization wants to set up mechanisms so that teams can share their learnings with other teams.

Which process blade is most likely to offer potential techniques to address this?

  • A . Support
  • B . Continuous Improvement
  • C . Governance
  • D . Portfolio Management

Reveal Solution Hide Solution

Correct Answer: B
Question #46

What is the role of management in Lean?

  • A . Ensure documentation is completed
  • B . Provide minimum viable products to the team.
  • C . Create awesome team environments.
  • D . Ensure decisions are not made regionally

Reveal Solution Hide Solution

Correct Answer: B
Question #47

True or False: On an Agile team, the team members accept or reject their own work at the iteration demo

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #48

Which of the following is the least suitable way to adopt disciplined agile delivery (DAD)?

  • A . Use any of the prescribed methods and follow to the letter
  • B . Take advise from the Choose your WoW book
  • C . Start with DAD
  • D . Work with an experienced coach

Reveal Solution Hide Solution

Correct Answer: A
Question #49

A team decided to skip the daily standup meetings as they were co-located and meeting daily was not adding value.

This is an example of:

  • A . Being awesome
  • B . Enterprise awareness
  • C . Context counts
  • D . Choice is good

Reveal Solution Hide Solution

Correct Answer: C
Question #50

Which method extends the Kaizen loop strategy to help teams identify techniques that are likely to work in their context?

  • A . Cross-team learning
  • B . Guided continuous improvement
  • C . Explicit workflow policies
  • D . Communities Of practice

Reveal Solution Hide Solution

Correct Answer: B

Question #51

Which characteristic describes a good user story according to the I.N.V.E.S.T. mnemonic?

  • A . Incremental
  • B . Valuable
  • C . Tangible
  • D . Satisfactory

Reveal Solution Hide Solution

Correct Answer: B
Question #52

What is the primary advantage of working in an agile team?

  • A . We can guarantee timely delivery of the product
  • B . We can specialize in an area of our choice
  • C . We can adjust quickly to changing customer needs
  • D . Customers will not need to bother much due to self-organized teams

Reveal Solution Hide Solution

Correct Answer: C
Question #53

Which process blade provides strategies to ensure successful interactions with the external world about your organization, products and offerings?

  • A . Portfolio management
  • B . Product Management
  • C . Sales
  • D . Business Operations
  • E . Marketing

Reveal Solution Hide Solution

Correct Answer: E
Question #54

What is a "definition of done"?

  • A . A checklist that tells the team when they can consider the user story done
  • B . A checklist that tells the team when they are done with the iteration
  • C . A checklist that tells the team when they are done estimating user stories

Reveal Solution Hide Solution

Correct Answer: B
Question #55

What are the three categories of process blades, according to Disciplined Agile (DA)? (Choose three)

  • A . Disciplined Project Management Office (PMO)
  • B . Disciplined Kanban
  • C . Disciplined DevOps
  • D . Disciplined Agile IT
  • E . Disciplined Agile Delivery (DAD)

Reveal Solution Hide Solution

Correct Answer: C,D,E
Question #56

True or False: "Choice is good" as a principle means that the team must present multiple products to its customers and let them make the choice

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B
Question #57

Which of these tools or techniques should be used to sequence work to deliver value quickly?

  • A . Planning Poker
  • B . Minimum business increment (MBI)
  • C . Work in process (WIP) limits
  • D . Minimum viable product (MVP)

Reveal Solution Hide Solution

Correct Answer: B
Question #58

Which of the following process goals require most of the effort when tailoring your agile strategy? (Choose two)

  • A . Improve Quality
  • B . Align with Enterprise Direction
  • C . Explore Scope
  • D . Address Changing Stakeholder Needs

Reveal Solution Hide Solution

Correct Answer: A,C
Question #59

Which of the following is a process goal in the Construction stage?

  • A . Explore scope
  • B . Develop test strategy
  • C . Prove architecture early
  • D . Form team
  • E . Ensure production readiness

Reveal Solution Hide Solution

Correct Answer: C
Question #60

The architecture of a product is usually proven in which phase of a project?

  • A . Elaboration
  • B . Construction
  • C . Inception
  • D . Transition

Reveal Solution Hide Solution

Correct Answer: B

Question #61

What are two of the ways that Disciplined Agile provides a solid foundation for business agility?

  • A . Creates awesome teams that foster joy.
  • B . Defines a framework for agility at scale.
  • C . Enforces adherence to organizational standards.
  • D . Describes the trade-offs associated with a range of options.

Reveal Solution Hide Solution

Correct Answer: B,C
Question #62

True or False: Any change or improvement in the process is likely to plateau unless efforts are put into constantly reviewing and revising it.

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: A
Question #63

Which of the following is an advantage of a project team as opposed to long standing product teams?

  • A . Greater motivation to learn and evolve the WoW
  • B . Greater focus on delivery and short term goals
  • C . Creates a long term focus
  • D . Brings work to the team rather than team to the work

Reveal Solution Hide Solution

Correct Answer: B
Question #64

What is the main role of the team lead?

  • A . Ensure that the team builds the product right
  • B . Ensure that the team builds the right product
  • C . Build the product
  • D . Coordinate the building of the product.

Reveal Solution Hide Solution

Correct Answer: D
Question #65

Which of the following is one of the 4 views of Disciplined Agile?

  • A . Mindset
  • B . Enterprise
  • C . Technology
  • D . Goals

Reveal Solution Hide Solution

Correct Answer: A
Question #66

Which is not a feature of a user story?

  • A . Achievable
  • B . Estimable
  • C . Testable
  • D . Negotiable

Reveal Solution Hide Solution

Correct Answer: A
Question #67

Which of the following is not a role for the team lead in a Disciplined Agile team?

  • A . Guiding the team through improvement actions
  • B . Helping the team collaborate
  • C . Providing timely decisions on priority and product roadmap
  • D . Helping the team evolve their WoW

Reveal Solution Hide Solution

Correct Answer: C
Question #68

Using Lean thinking, we should be managing

  • A . The value stream
  • B . Each step of the work
  • C . Our people
  • D . By letting people figure out what they need to do

Reveal Solution Hide Solution

Correct Answer: A
Question #69

Which of the following milestones represent a DA project moving from Construction to Transition stage?

  • A . Production ready
  • B . Sufficient functionality
  • C . Proven architecture
  • D . Continued viability
  • E . Stakeholder vision

Reveal Solution Hide Solution

Correct Answer: B
Question #70

True or False: Delight customers as a principle means never to exceed expectations of the customers but to just about meet them

  • A . True
  • B . False

Reveal Solution Hide Solution

Correct Answer: B