In which of the following cases, would an organization be more prone to risk acceptance vs. risk mitigation?
A . The organization uses exclusively a qualitative process to measure risk
B . The organization’s risk tolerance is low
C . The organization uses exclusively a quantitative process to measure risk
D . The organization’s risk tolerance is high
Answer: D
Latest 712-50 Dumps Valid Version with 398 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund