Huawei H20-681-ENU Huawei Certified Field Specialist -Smart PV Controller Online Training

Exam4Training is the superlative site from where you can easily get Huawei H20-681-ENU Huawei Certified Field Specialist -Smart PV Controller Online Training. Exam4Training is the most reliable resource for your Huawei H20-681-ENU exam. At Exam4Training provide Huawei H20-681-ENU Huawei Certified Field Specialist -Smart PV Controller Online Training, like actual exam questions, dumps and etc. All the HCS-Field-Smart PV Controller H20-681-ENU material is accordingly set by subject matters experts. Exam4Training also offer you to try the free demo, before purchase. Also, we have a refund policy if you fail in the exam so you can claim for your refund confidently.

Page 1 of 2

1. The NetEco1000S is an equipment-level monitoring software for inverters. It is mainly used in SUN2000, SUN8000 and third-party inverters.

2. The device that cannot be upgraded by the NetEco1000S system for remote software is ()

3. About the description of SmartLogger1000 and SmartLogger2000, which is incorrect? (Multiple Choice)

4. Huawei Smart Array Controller SmartACU2000B is recommended to be larger than () mm from the ground when installing.

5. About Huawei's smart photovoltaic solution grounding system design, which of the following is correct? (Multiple Choice)

6. When the debugging of the Huawei PLC communication network is started, which of the operation description of setting the anti-crosstalk is correct? (Multiple Choice)

7. When installing the AC line of the Huawei SUN2000 inverter, it is recommended that the stripping length of the insulation layer be 2mm~3mm longer than the crimping area of the OT terminal sub cable for convenient wiring. After pressing the terminal, the place of line needs to be covered with a heat shrinkable T bush or insulating rubber tape.

8. During the operation of Huawei SUN2000L household inverter, the inverter “DC SWITCH” can be directly set to “OFF” for shutdown operation.

9. Which of the following design is not suitable for a mountain photovoltaic power station system?

10. The Huawei PID module adjusts the photovoltaic panel PV+ or PV- voltage to earth by injecting voltage between N line and ground line of the isolation transformer, to realize the inhibition of photovoltaic panel PID effect.


 

Latest H20-681-ENU Dumps Valid Version with 192 Q&As

Latest And Valid Q&A | 90 Days Free Update | Once Fail, Full Refund

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

  • Sign up
Lost your password? Please enter your username or email address. You will receive a link to create a new password via email.
We do not share your personal details with anyone.