How will this change impact the customer environment?

Your customer has 6 logical enclosures spanning 18 HPE Synergy frames. The customer needs to add one more logical enclosure based on 5 HPE Synergy frames

How will this change impact the customer environment?
A . The customer can add a new logical enclosure to the existing setup because the maximum number of logical enclosures in a single management ring is not reached.
B . The customer has to expand the management ring capacity either by adding HPE Composer 2 modules or adding memory to reach 128GB per module.
C . The customer has to create a new management ring for new logical enclosure because the maximum number of frames m a single management ring is reached.
D . The customer can add a new logical enclosure to an existing setup once all required licenses are added to HPE OneView and associated with the new frames.

Answer: C

Explanation:

HPE Synergy management rings have a maximum capacity for the number of frames they can manage. With 18 frames already managed in 6 logical enclosures, adding 5 more frames would exceed this capacity. Therefore, the customer needs to create a new management ring for the new logical enclosure to ensure proper management and operation.

Reference: HPE Synergy Management Guide