How does applying calculated metrics in a project benefit the data analysis process?
How does applying calculated metrics in a project benefit the data analysis process?
A . By reducing the need for external data sources
B . By providing deeper insights through custom formulations
C . By increasing the data processing time
D . By simplifying user interfaces
Answer: B